Our performance

Read about our performance to find out how we’re delivering on our commitments to our customers.  Here you can take a detailed look at our performance for the regulatory periods known as RIIO-GD1 (2013 – 2021) and RIIO-GD2 (2021-2026)

You’ll find a brief commentary on what each regulatory output means and how we performed against our targets.

RIIO-GD1 (2013 – 2021)

Here you can take a detailed look at our performance since the start of the regulatory period known as RIIO-GD1 (2013 – 2021).

You’ll find a brief commentary on what each regulatory output means and how we performed against our targets.

Keeping our network safe and sound

As the region’s gas network operator, safety is paramount in everything we do.  Keeping our customers and colleagues safe and sound is our overriding priority and we’re constantly investing in our network to make it safer and less prone to leaks.

  • 2013/14
  • 2014/15
  • 2015/16
  • 2016/17
  • 2017/18
  • 2018/19
  • 2019/20
  • 2020/21

Year: 2013/14

Emergency Response

SummaryTargetActual
Amount of uncontrolled gas escapes attended within 1 hourOur engineers need to get out quickly to gas escapes, and we were always comfortably ahead of our statutory response times when it came to responding to urgent escapes97%99.85%
Amount of controlled gas escapes within 2 hoursSome gas escapes can be responded to within a two hour window, where the risk to the customer is deemed lower. We were always comfortably ahead of our targets for the year throughout RIIO GD1.97%99.97%

Repair

SummaryTargetActual
Annual riskWe work out a total risk score for all pipes which require a repair. The score is based on a wide range of criteria, and is helpful in allowing us to prioritise our repair work. Our focus on repairing more challenging pipes during the pandemic helped us to comfortably beat our risk target in the final year of RIIO GD1, consistent with our outperformance every year since 2013.<34.5m34.4m
Amount of repairs completed within 12 hoursThis refers to emergency repairs on our network. We were comfortably ahead of our target throughout RIIO GD1.62.50%62.3%

Mains replacement

SummaryTargetActual
Risk removed (incidents/year* 10-6)Every metal pipe is given a risk score, based on factors such as the number of gas escapes. The overall ‘risk removed’ figure therefore gives a snapshot of our progress in making the network safer. Good news – we were ahead of target in 2020/21 and consistently year on year throughout RIIO GD1, exceeding our eight year target of 111,192, by 97%.13,89843,119
Number of gas escapes in building eventsA measure of the number of gas escapes which resulted in gas finding its way into a building – presenting a potential safety risk to customers. There were 49 instances of gas in buildings in the final year of RIIO GD1 and we’re continuing to work to reduce this number further.14456
Number of fractures or corrosion failuresOld metal pipes are subject to fractures or corrosion. We’re gradually replacing them with new plastic pipes to reduce these types of failure, and comfortably beat our annual target year on year throughout RIIO GD1.2,742815
Length of main taken 'off risk' (funded)Replacing old metal pipes with modern plastic ones dramatically reduces the risk of gas escapes. We replaced 3,886 km of old metal pipes during RIIO GD1, just shy of our 3,975 km target. This was due to some of our essential work being paused due to the Covid-19 pandemic, however we’re making up the shortfall in RIIO GD2.448 km483.6km
Length of main taken 'off risk' (customer driven)This refers to the length of old pipes replaced while carrying out work at a customer’s request, such as diverting a pipe. We cannot influence this output, given it is customer driven, and were behind target throughout RIIO GD1. Lots of disparate factors can influence this statistic, such as the health of the economy. More prosperity means customers invest more in property (e.g. building extensions or new builds) – and that means more private pipes get replaced.15.4km1.8km
Number of non-PE services replacedService pipes are the connecting pipes which link a customer’s home or business to the gas mains in the street. We made a decision to focus this activity where it delivered most value for our customers and upgrade service pipes as part of planned work to modernise our network, rather than carrying out bulk service renewals that might not add value for our customers. The Covid-19 pandemic saw a further fall in the number of service pipes replaced while we had limited access to customers homes.30,93229,305
Asset health and risk metricsWe are constantly assessing the overall health of our assets (pipes and associated equipment) and the level of risk to inform how and where we invest in the future.Phased planOn track

Major accident hazard protection

SummaryTargetActual
Compliance with the Control of Major Accident Hazard regulations (number of breaches)We are required to show that we have fully complied with these essential Health and Safety Executive regulations, by, for example, having a major accident prevention policy in place.Zero-
Compliance with the Gas Safety Management Regulations (number of breaches)We are required to show that we have fully complied with these essential Health and Safety Executive regulations.Zero-
Sub-deduct network 'off risk'by the end of RIIOSub-deduct networks are parts of the gas network where ownership and responsibility are unclear – presenting a potential safety risk. Through re-engineering these networks, or establishing third party acceptance of responsibility, we have now taken all sites off-risk.1369

Year: 2014/15

Emergency Response

SummaryTargetActual
Amount of uncontrolled gas escapes attended within 1 hourOur engineers need to get out quickly to gas escapes, and we were always comfortably ahead of our statutory response times when it came to responding to urgent escapes97%99.85%
Amount of controlled gas escapes within 2 hoursSome gas escapes can be responded to within a two hour window, where the risk to the customer is deemed lower. We were always comfortably ahead of our targets for the year throughout RIIO GD1.97%99.99%

Repair

SummaryTargetActual
Annual riskWe work out a total risk score for all pipes which require a repair. The score is based on a wide range of criteria, and is helpful in allowing us to prioritise our repair work. Our focus on repairing more challenging pipes during the pandemic helped us to comfortably beat our risk target in the final year of RIIO GD1, consistent with our outperformance every year since 2013.<34.5m24.8m
Amount of repairs completed within 12 hoursThis refers to emergency repairs on our network. We were comfortably ahead of our target throughout RIIO GD1.62.50%62.9%

Mains replacement

SummaryTargetActual
Risk removed (incidents/year* 10-6)Every metal pipe is given a risk score, based on factors such as the number of gas escapes. The overall ‘risk removed’ figure therefore gives a snapshot of our progress in making the network safer. Good news – we were ahead of target in 2020/21 and consistently year on year throughout RIIO GD1, exceeding our eight year target of 111,192, by 97%.13,89841,2123
Number of gas escapes in building eventsA measure of the number of gas escapes which resulted in gas finding its way into a building – presenting a potential safety risk to customers. There were 49 instances of gas in buildings in the final year of RIIO GD1 and we’re continuing to work to reduce this number further.14477
Number of fractures or corrosion failuresOld metal pipes are subject to fractures or corrosion. We’re gradually replacing them with new plastic pipes to reduce these types of failure, and comfortably beat our annual target year on year throughout RIIO GD1.2,742883
Length of main taken 'off risk' (funded)Replacing old metal pipes with modern plastic ones dramatically reduces the risk of gas escapes. We replaced 3,886 km of old metal pipes during RIIO GD1, just shy of our 3,975 km target. This was due to some of our essential work being paused due to the Covid-19 pandemic, however we’re making up the shortfall in RIIO GD2.448 km519.4km
Length of main taken 'off risk' (customer driven)This refers to the length of old pipes replaced while carrying out work at a customer’s request, such as diverting a pipe. We cannot influence this output, given it is customer driven, and were behind target throughout RIIO GD1. Lots of disparate factors can influence this statistic, such as the health of the economy. More prosperity means customers invest more in property (e.g. building extensions or new builds) – and that means more private pipes get replaced.15.4km2.1km
Number of non-PE services replacedService pipes are the connecting pipes which link a customer’s home or business to the gas mains in the street. We made a decision to focus this activity where it delivered most value for our customers and upgrade service pipes as part of planned work to modernise our network, rather than carrying out bulk service renewals that might not add value for our customers. The Covid-19 pandemic saw a further fall in the number of service pipes replaced while we had limited access to customers homes.30,93229,609
Asset health and risk metricsWe are constantly assessing the overall health of our assets (pipes and associated equipment) and the level of risk to inform how and where we invest in the future.Phased planOn track

Major accident hazard protection

SummaryTargetActual
Compliance with the Control of Major Accident Hazard regulations (number of breaches)We are required to show that we have fully complied with these essential Health and Safety Executive regulations, by, for example, having a major accident prevention policy in place.Zero-
Compliance with the Gas Safety Management Regulations (number of breaches)We are required to show that we have fully complied with these essential Health and Safety Executive regulations.Zero-
Sub-deduct network 'off risk'by the end of RIIOSub-deduct networks are parts of the gas network where ownership and responsibility are unclear – presenting a potential safety risk. Through re-engineering these networks, or establishing third party acceptance of responsibility, we have now taken all sites off-risk.13669

Year: 2015/16

Emergency Response

SummaryTargetActual
Amount of uncontrolled gas escapes attended within 1 hourOur engineers need to get out quickly to gas escapes, and we were always comfortably ahead of our statutory response times when it came to responding to urgent escapes97%99.76%
Amount of controlled gas escapes within 2 hoursSome gas escapes can be responded to within a two hour window, where the risk to the customer is deemed lower. We were always comfortably ahead of our targets for the year throughout RIIO GD1.97%99.96%

Repair

SummaryTargetActual
Annual riskWe work out a total risk score for all pipes which require a repair. The score is based on a wide range of criteria, and is helpful in allowing us to prioritise our repair work. Our focus on repairing more challenging pipes during the pandemic helped us to comfortably beat our risk target in the final year of RIIO GD1, consistent with our outperformance every year since 2013.<34.5m18.6m
Amount of repairs completed within 12 hoursThis refers to emergency repairs on our network. We were comfortably ahead of our target throughout RIIO GD1.62.50%64.4%

Mains replacement

SummaryTargetActual
Risk removed (incidents/year* 10-6)Every metal pipe is given a risk score, based on factors such as the number of gas escapes. The overall ‘risk removed’ figure therefore gives a snapshot of our progress in making the network safer. Good news – we were ahead of target in 2020/21 and consistently year on year throughout RIIO GD1, exceeding our eight year target of 111,192, by 97%.13,89829,893
Number of gas escapes in building eventsA measure of the number of gas escapes which resulted in gas finding its way into a building – presenting a potential safety risk to customers. There were 49 instances of gas in buildings in the final year of RIIO GD1 and we’re continuing to work to reduce this number further.14458
Number of fractures or corrosion failuresOld metal pipes are subject to fractures or corrosion. We’re gradually replacing them with new plastic pipes to reduce these types of failure, and comfortably beat our annual target year on year throughout RIIO GD1.2,742685
Length of main taken 'off risk' (funded)Replacing old metal pipes with modern plastic ones dramatically reduces the risk of gas escapes. We replaced 3,886 km of old metal pipes during RIIO GD1, just shy of our 3,975 km target. This was due to some of our essential work being paused due to the Covid-19 pandemic, however we’re making up the shortfall in RIIO GD2.448 km461.3km
Length of main taken 'off risk' (customer driven)This refers to the length of old pipes replaced while carrying out work at a customer’s request, such as diverting a pipe. We cannot influence this output, given it is customer driven, and were behind target throughout RIIO GD1. Lots of disparate factors can influence this statistic, such as the health of the economy. More prosperity means customers invest more in property (e.g. building extensions or new builds) – and that means more private pipes get replaced.15.4km2.9km
Number of non-PE services replacedService pipes are the connecting pipes which link a customer’s home or business to the gas mains in the street. We made a decision to focus this activity where it delivered most value for our customers and upgrade service pipes as part of planned work to modernise our network, rather than carrying out bulk service renewals that might not add value for our customers. The Covid-19 pandemic saw a further fall in the number of service pipes replaced while we had limited access to customers homes.30,93227,579
Asset health and risk metricsWe are constantly assessing the overall health of our assets (pipes and associated equipment) and the level of risk to inform how and where we invest in the future.Phased planOn track

Major accident hazard protection

SummaryTargetActual
Compliance with the Control of Major Accident Hazard regulations (number of breaches)We are required to show that we have fully complied with these essential Health and Safety Executive regulations, by, for example, having a major accident prevention policy in place.Zero-
Compliance with the Gas Safety Management Regulations (number of breaches)We are required to show that we have fully complied with these essential Health and Safety Executive regulations.Zero-
Sub-deduct network 'off risk'by the end of RIIOSub-deduct networks are parts of the gas network where ownership and responsibility are unclear – presenting a potential safety risk. Through re-engineering these networks, or establishing third party acceptance of responsibility, we have now taken all sites off-risk.13634

Year: 2016/17

Emergency Response

SummaryTargetActual
Amount of uncontrolled gas escapes attended within 1 hourOur engineers need to get out quickly to gas escapes, and we were always comfortably ahead of our statutory response times when it came to responding to urgent escapes97%99.76%
Amount of controlled gas escapes within 2 hoursSome gas escapes can be responded to within a two hour window, where the risk to the customer is deemed lower. We were always comfortably ahead of our targets for the year throughout RIIO GD1.97%99.97%

Repair

SummaryTargetActual
Annual riskWe work out a total risk score for all pipes which require a repair. The score is based on a wide range of criteria, and is helpful in allowing us to prioritise our repair work. Our focus on repairing more challenging pipes during the pandemic helped us to comfortably beat our risk target in the final year of RIIO GD1, consistent with our outperformance every year since 2013.<34.5m17.4m
Amount of repairs completed within 12 hoursThis refers to emergency repairs on our network. We were comfortably ahead of our target throughout RIIO GD1.62.50%62.3%

Mains replacement

SummaryTargetActual
Risk removed (incidents/year* 10-6)Every metal pipe is given a risk score, based on factors such as the number of gas escapes. The overall ‘risk removed’ figure therefore gives a snapshot of our progress in making the network safer. Good news – we were ahead of target in 2020/21 and consistently year on year throughout RIIO GD1, exceeding our eight year target of 111,192, by 97%.13,89826,727
Number of gas escapes in building eventsA measure of the number of gas escapes which resulted in gas finding its way into a building – presenting a potential safety risk to customers. There were 49 instances of gas in buildings in the final year of RIIO GD1 and we’re continuing to work to reduce this number further.14452
Number of fractures or corrosion failuresOld metal pipes are subject to fractures or corrosion. We’re gradually replacing them with new plastic pipes to reduce these types of failure, and comfortably beat our annual target year on year throughout RIIO GD1.2,742683
Length of main taken 'off risk' (funded)Replacing old metal pipes with modern plastic ones dramatically reduces the risk of gas escapes. We replaced 3,886 km of old metal pipes during RIIO GD1, just shy of our 3,975 km target. This was due to some of our essential work being paused due to the Covid-19 pandemic, however we’re making up the shortfall in RIIO GD2.448 km473.6km
Length of main taken 'off risk' (customer driven)This refers to the length of old pipes replaced while carrying out work at a customer’s request, such as diverting a pipe. We cannot influence this output, given it is customer driven, and were behind target throughout RIIO GD1. Lots of disparate factors can influence this statistic, such as the health of the economy. More prosperity means customers invest more in property (e.g. building extensions or new builds) – and that means more private pipes get replaced.15.4km1.9km
Number of non-PE services replacedService pipes are the connecting pipes which link a customer’s home or business to the gas mains in the street. We made a decision to focus this activity where it delivered most value for our customers and upgrade service pipes as part of planned work to modernise our network, rather than carrying out bulk service renewals that might not add value for our customers. The Covid-19 pandemic saw a further fall in the number of service pipes replaced while we had limited access to customers homes.30,93229,275
Asset health and risk metricsWe are constantly assessing the overall health of our assets (pipes and associated equipment) and the level of risk to inform how and where we invest in the future.Phased planOn track

Major accident hazard protection

SummaryTargetActual
Compliance with the Control of Major Accident Hazard regulations (number of breaches)We are required to show that we have fully complied with these essential Health and Safety Executive regulations, by, for example, having a major accident prevention policy in place.Zero-
Compliance with the Gas Safety Management Regulations (number of breaches)We are required to show that we have fully complied with these essential Health and Safety Executive regulations.Zero-
Sub-deduct network 'off risk'by the end of RIIOSub-deduct networks are parts of the gas network where ownership and responsibility are unclear – presenting a potential safety risk. Through re-engineering these networks, or establishing third party acceptance of responsibility, we have now taken all sites off-risk.1369

Year: 2017/18

Emergency Response

SummaryTargetActual
Amount of uncontrolled gas escapes attended within 1 hourOur engineers need to get out quickly to gas escapes, and we were always comfortably ahead of our statutory response times when it came to responding to urgent escapes97%99.61%
Amount of controlled gas escapes within 2 hoursSome gas escapes can be responded to within a two hour window, where the risk to the customer is deemed lower. We were always comfortably ahead of our targets for the year throughout RIIO GD1.97%99.72%

Repair

SummaryTargetActual
Annual riskWe work out a total risk score for all pipes which require a repair. The score is based on a wide range of criteria, and is helpful in allowing us to prioritise our repair work. Our focus on repairing more challenging pipes during the pandemic helped us to comfortably beat our risk target in the final year of RIIO GD1, consistent with our outperformance every year since 2013.<34.5m19.3m
Amount of repairs completed within 12 hoursThis refers to emergency repairs on our network. We were comfortably ahead of our target throughout RIIO GD1.62.50%66.1%

Mains replacement

SummaryTargetActual
Risk removed (incidents/year* 10-6)Every metal pipe is given a risk score, based on factors such as the number of gas escapes. The overall ‘risk removed’ figure therefore gives a snapshot of our progress in making the network safer. Good news – we were ahead of target in 2020/21 and consistently year on year throughout RIIO GD1, exceeding our eight year target of 111,192, by 97%.13,89823,439
Number of gas escapes in building eventsA measure of the number of gas escapes which resulted in gas finding its way into a building – presenting a potential safety risk to customers. There were 49 instances of gas in buildings in the final year of RIIO GD1 and we’re continuing to work to reduce this number further.14464
Number of fractures or corrosion failuresOld metal pipes are subject to fractures or corrosion. We’re gradually replacing them with new plastic pipes to reduce these types of failure, and comfortably beat our annual target year on year throughout RIIO GD1.2,742689
Length of main taken 'off risk' (funded)Replacing old metal pipes with modern plastic ones dramatically reduces the risk of gas escapes. We replaced 3,886 km of old metal pipes during RIIO GD1, just shy of our 3,975 km target. This was due to some of our essential work being paused due to the Covid-19 pandemic, however we’re making up the shortfall in RIIO GD2.448 km514.4km
Length of main taken 'off risk' (customer driven)This refers to the length of old pipes replaced while carrying out work at a customer’s request, such as diverting a pipe. We cannot influence this output, given it is customer driven, and were behind target throughout RIIO GD1. Lots of disparate factors can influence this statistic, such as the health of the economy. More prosperity means customers invest more in property (e.g. building extensions or new builds) – and that means more private pipes get replaced.15.4km2.0km
Number of non-PE services replacedService pipes are the connecting pipes which link a customer’s home or business to the gas mains in the street. We made a decision to focus this activity where it delivered most value for our customers and upgrade service pipes as part of planned work to modernise our network, rather than carrying out bulk service renewals that might not add value for our customers. The Covid-19 pandemic saw a further fall in the number of service pipes replaced while we had limited access to customers homes.30,93229,906
Asset health and risk metricsWe are constantly assessing the overall health of our assets (pipes and associated equipment) and the level of risk to inform how and where we invest in the future.Phased planOn track

Major accident hazard protection

SummaryTargetActual
Compliance with the Control of Major Accident Hazard regulations (number of breaches)We are required to show that we have fully complied with these essential Health and Safety Executive regulations, by, for example, having a major accident prevention policy in place.Zero-
Compliance with the Gas Safety Management Regulations (number of breaches)We are required to show that we have fully complied with these essential Health and Safety Executive regulations.Zero-
Sub-deduct network 'off risk'by the end of RIIOSub-deduct networks are parts of the gas network where ownership and responsibility are unclear – presenting a potential safety risk. Through re-engineering these networks, or establishing third party acceptance of responsibility, we have now taken all sites off-risk.136-

Year: 2018/19

Emergency Response

SummaryTargetActual
Amount of uncontrolled gas escapes attended within 1 hourOur engineers need to get out quickly to gas escapes, and we were always comfortably ahead of our statutory response times when it came to responding to urgent escapes97%99.75%
Amount of controlled gas escapes within 2 hoursSome gas escapes can be responded to within a two hour window, where the risk to the customer is deemed lower. We were always comfortably ahead of our targets for the year throughout RIIO GD1.97%99.94%

Repair

SummaryTargetActual
Annual riskWe work out a total risk score for all pipes which require a repair. The score is based on a wide range of criteria, and is helpful in allowing us to prioritise our repair work. Our focus on repairing more challenging pipes during the pandemic helped us to comfortably beat our risk target in the final year of RIIO GD1, consistent with our outperformance every year since 2013.<34.5m23.6m
Amount of repairs completed within 12 hoursThis refers to emergency repairs on our network. We were comfortably ahead of our target throughout RIIO GD1.62.50%68.4%

Mains replacement

SummaryTargetActual
Risk removed (incidents/year* 10-6)Every metal pipe is given a risk score, based on factors such as the number of gas escapes. The overall ‘risk removed’ figure therefore gives a snapshot of our progress in making the network safer. Good news – we were ahead of target in 2020/21 and consistently year on year throughout RIIO GD1, exceeding our eight year target of 111,192, by 97%.13,89819,590
Number of gas escapes in building eventsA measure of the number of gas escapes which resulted in gas finding its way into a building – presenting a potential safety risk to customers. There were 49 instances of gas in buildings in the final year of RIIO GD1 and we’re continuing to work to reduce this number further.14453
Number of fractures or corrosion failuresOld metal pipes are subject to fractures or corrosion. We’re gradually replacing them with new plastic pipes to reduce these types of failure, and comfortably beat our annual target year on year throughout RIIO GD1.2,742678
Length of main taken 'off risk' (funded)Replacing old metal pipes with modern plastic ones dramatically reduces the risk of gas escapes. We replaced 3,886 km of old metal pipes during RIIO GD1, just shy of our 3,975 km target. This was due to some of our essential work being paused due to the Covid-19 pandemic, however we’re making up the shortfall in RIIO GD2.448 km522.96km
Length of main taken 'off risk' (customer driven)This refers to the length of old pipes replaced while carrying out work at a customer’s request, such as diverting a pipe. We cannot influence this output, given it is customer driven, and were behind target throughout RIIO GD1. Lots of disparate factors can influence this statistic, such as the health of the economy. More prosperity means customers invest more in property (e.g. building extensions or new builds) – and that means more private pipes get replaced.15.4km2.2km
Number of non-PE services replacedService pipes are the connecting pipes which link a customer’s home or business to the gas mains in the street. We made a decision to focus this activity where it delivered most value for our customers and upgrade service pipes as part of planned work to modernise our network, rather than carrying out bulk service renewals that might not add value for our customers. The Covid-19 pandemic saw a further fall in the number of service pipes replaced while we had limited access to customers homes.30,93230,984
Asset health and risk metricsWe are constantly assessing the overall health of our assets (pipes and associated equipment) and the level of risk to inform how and where we invest in the future.Phased planOn track

Major accident hazard protection

SummaryTargetActual
Compliance with the Control of Major Accident Hazard regulations (number of breaches)We are required to show that we have fully complied with these essential Health and Safety Executive regulations, by, for example, having a major accident prevention policy in place.Zero-
Compliance with the Gas Safety Management Regulations (number of breaches)We are required to show that we have fully complied with these essential Health and Safety Executive regulations.Zero-
Sub-deduct network 'off risk'by the end of RIIOSub-deduct networks are parts of the gas network where ownership and responsibility are unclear – presenting a potential safety risk. Through re-engineering these networks, or establishing third party acceptance of responsibility, we have now taken all sites off-risk.1362

Year: 2019/20

Emergency Response

SummaryTargetActual
Amount of uncontrolled gas escapes attended within 1 hourOur engineers need to get out quickly to gas escapes, and we were always comfortably ahead of our statutory response times when it came to responding to urgent escapes97%99.83%
Amount of controlled gas escapes within 2 hoursSome gas escapes can be responded to within a two hour window, where the risk to the customer is deemed lower. We were always comfortably ahead of our targets for the year throughout RIIO GD1.97%99.29%

Repair

SummaryTargetActual
Annual riskWe work out a total risk score for all pipes which require a repair. The score is based on a wide range of criteria, and is helpful in allowing us to prioritise our repair work. Our focus on repairing more challenging pipes during the pandemic helped us to comfortably beat our risk target in the final year of RIIO GD1, consistent with our outperformance every year since 2013.<34.5m23.0m
Amount of repairs completed within 12 hoursThis refers to emergency repairs on our network. We were comfortably ahead of our target throughout RIIO GD1.62.50%64.3%

Mains replacement

SummaryTargetActual
Risk removed (incidents/year* 10-6)Every metal pipe is given a risk score, based on factors such as the number of gas escapes. The overall ‘risk removed’ figure therefore gives a snapshot of our progress in making the network safer. Good news – we were ahead of target in 2020/21 and consistently year on year throughout RIIO GD1, exceeding our eight year target of 111,192, by 97%.13,89820,268
Number of gas escapes in building eventsA measure of the number of gas escapes which resulted in gas finding its way into a building – presenting a potential safety risk to customers. There were 49 instances of gas in buildings in the final year of RIIO GD1 and we’re continuing to work to reduce this number further.14449
Number of fractures or corrosion failuresOld metal pipes are subject to fractures or corrosion. We’re gradually replacing them with new plastic pipes to reduce these types of failure, and comfortably beat our annual target year on year throughout RIIO GD1.2,742569
Length of main taken 'off risk' (funded)Replacing old metal pipes with modern plastic ones dramatically reduces the risk of gas escapes. We replaced 3,886 km of old metal pipes during RIIO GD1, just shy of our 3,975 km target. This was due to some of our essential work being paused due to the Covid-19 pandemic, however we’re making up the shortfall in RIIO GD2.448 km495.5km
Length of main taken 'off risk' (customer driven)This refers to the length of old pipes replaced while carrying out work at a customer’s request, such as diverting a pipe. We cannot influence this output, given it is customer driven, and were behind target throughout RIIO GD1. Lots of disparate factors can influence this statistic, such as the health of the economy. More prosperity means customers invest more in property (e.g. building extensions or new builds) – and that means more private pipes get replaced.15.4km1.6km
Number of non-PE services replacedService pipes are the connecting pipes which link a customer’s home or business to the gas mains in the street. We made a decision to focus this activity where it delivered most value for our customers and upgrade service pipes as part of planned work to modernise our network, rather than carrying out bulk service renewals that might not add value for our customers. The Covid-19 pandemic saw a further fall in the number of service pipes replaced while we had limited access to customers homes.30,93227,667
Asset health and risk metricsWe are constantly assessing the overall health of our assets (pipes and associated equipment) and the level of risk to inform how and where we invest in the future.Phased planOn track

Major accident hazard protection

SummaryTargetActual
Compliance with the Control of Major Accident Hazard regulations (number of breaches)We are required to show that we have fully complied with these essential Health and Safety Executive regulations, by, for example, having a major accident prevention policy in place.Zero-
Compliance with the Gas Safety Management Regulations (number of breaches)We are required to show that we have fully complied with these essential Health and Safety Executive regulations.Zero-
Sub-deduct network 'off risk'by the end of RIIOSub-deduct networks are parts of the gas network where ownership and responsibility are unclear – presenting a potential safety risk. Through re-engineering these networks, or establishing third party acceptance of responsibility, we have now taken all sites off-risk.13612

Year: 2020/21

Emergency Response

SummaryTargetActual
Amount of uncontrolled gas escapes attended within 1 hourOur engineers need to get out quickly to gas escapes, and we were always comfortably ahead of our statutory response times when it came to responding to urgent escapes97%99.8%
Amount of controlled gas escapes within 2 hoursSome gas escapes can be responded to within a two hour window, where the risk to the customer is deemed lower. We were always comfortably ahead of our targets for the year throughout RIIO GD1.97%99.9%

Repair

SummaryTargetActual
Annual riskWe work out a total risk score for all pipes which require a repair. The score is based on a wide range of criteria, and is helpful in allowing us to prioritise our repair work. Our focus on repairing more challenging pipes during the pandemic helped us to comfortably beat our risk target in the final year of RIIO GD1, consistent with our outperformance every year since 2013.<34.5m12.5m
Amount of repairs completed within 12 hoursThis refers to emergency repairs on our network. We were comfortably ahead of our target throughout RIIO GD1.62.50%65.1%

Mains replacement

SummaryTargetActual
Risk removed (incidents/year* 10-6)Every metal pipe is given a risk score, based on factors such as the number of gas escapes. The overall ‘risk removed’ figure therefore gives a snapshot of our progress in making the network safer. Good news – we were ahead of target in 2020/21 and consistently year on year throughout RIIO GD1, exceeding our eight year target of 111,192, by 97%.13,89815,505
Number of gas escapes in building eventsA measure of the number of gas escapes which resulted in gas finding its way into a building – presenting a potential safety risk to customers. There were 49 instances of gas in buildings in the final year of RIIO GD1 and we’re continuing to work to reduce this number further.14449
Number of fractures or corrosion failuresOld metal pipes are subject to fractures or corrosion. We’re gradually replacing them with new plastic pipes to reduce these types of failure, and comfortably beat our annual target year on year throughout RIIO GD1.2,742814
Length of main taken 'off risk' (funded)Replacing old metal pipes with modern plastic ones dramatically reduces the risk of gas escapes. We replaced 3,886 km of old metal pipes during RIIO GD1, just shy of our 3,975 km target. This was due to some of our essential work being paused due to the Covid-19 pandemic, however we’re making up the shortfall in RIIO GD2.448 km394.5km
Length of main taken 'off risk' (customer driven)This refers to the length of old pipes replaced while carrying out work at a customer’s request, such as diverting a pipe. We cannot influence this output, given it is customer driven, and were behind target throughout RIIO GD1. Lots of disparate factors can influence this statistic, such as the health of the economy. More prosperity means customers invest more in property (e.g. building extensions or new builds) – and that means more private pipes get replaced.15.4km2.2km
Number of non-PE services replacedService pipes are the connecting pipes which link a customer’s home or business to the gas mains in the street. We made a decision to focus this activity where it delivered most value for our customers and upgrade service pipes as part of planned work to modernise our network, rather than carrying out bulk service renewals that might not add value for our customers. The Covid-19 pandemic saw a further fall in the number of service pipes replaced while we had limited access to customers homes.30,93215,699
Asset health and risk metricsWe are constantly assessing the overall health of our assets (pipes and associated equipment) and the level of risk to inform how and where we invest in the future.Phased planOn track

Major accident hazard protection

SummaryTargetActual
Compliance with the Control of Major Accident Hazard regulations (number of breaches)We are required to show that we have fully complied with these essential Health and Safety Executive regulations, by, for example, having a major accident prevention policy in place.Zero-
Compliance with the Gas Safety Management Regulations (number of breaches)We are required to show that we have fully complied with these essential Health and Safety Executive regulations.Zero-
Sub-deduct network 'off risk'by the end of RIIOSub-deduct networks are parts of the gas network where ownership and responsibility are unclear – presenting a potential safety risk. Through re-engineering these networks, or establishing third party acceptance of responsibility, we have now taken all sites off-risk.1361

Keeping the gas flowing

We’re investing in our network to continue to heat homes and businesses across the North of England for years to come and ensure that it is more reliable than ever.

  • 2013/14
  • 2014/15
  • 2015/16
  • 2016/17
  • 2017/18
  • 2018/19
  • 2019/20
  • 2020/21

Year: 2013/14

Loss of Supply

SummaryTargetActual
Number of planned interruptionsInterruptions to the gas supply for which customers were given prior notice (e.g. by letter). Planned mains replacement work is the most common scenario here. The stats show that the number of planned interruptions was less than our target for the year. We also comfortably beat our eight year target of 517,170 planned interruptions.64,64657,434
Number of unplanned interruptionsInterruptions to the gas supply caused by unplanned issues – such as gas leaks, or water finding its way into the pipe network. We finished RIIO GD1, comfortably ahead of our 8 year target of 103,677.12,96013,034

Repair

SummaryTargetActual
Annual riskWe work out a total risk score for all pipes which require a repair. The score is based on a wide range of criteria, and is helpful in allowing us to prioritise our repair work. Our focus on repairing more challenging pipes during the pandemic helped us to comfortably beat our risk target in the final year of RIIO GD1, consistent with our outperformance every year since 2013.<34.5m34.4m
Amount of repairs completed within 12 hoursThis refers to emergency repairs on our network. We were comfortably ahead of our target throughout RIIO GD1.62.50%62.3%

Network Capacity

SummaryTargetActual
Meeting NGN's 1 in 20 planning standard (MWh pa)This output requires our network to have enough capacity to ensure customers’ gas supplies are not interrupted during periods of highest demand (known as a one in 20 year event). Estimates of peak demand have actually been falling since 2005, and we have met our annual target throughout much of RIIO GD1.499,186500,315
PRI utilisation and capacityPressure Reduction Installations (PRI) reduce the pressure of gas before it is distributed to homes and businesses. To meet our obligations, assets need to be technically compliant and able to meet required volumes. We fell behind our target during the final year of RIIO GD1 due to a number of factors outside of our control, however overall our performance throughout the eight year period was on track.Phased planOn track

Network Reliability, maintaining operational performance

SummaryTargetActual
Percentage by volume of network meter errorsWe are responsible for monitoring and reporting the accuracy of the meters we use to measure the movement of gas from the National Transmission System into our network. We consistently met our annual target throughout RIIO GD1.<0.1% pa<0.002%
Number and duration of telemetered faultsThis target covers our response to telemetry faults (i.e. faults on equipment used to measure and record key data) on our above ground assets. We hit our target year on year throughout RIIO GD1.120105
Pressure System Safety Regulation FaultsStatutory inspections are carried out on our network. We hit our target year on year throughout RIIO GD1.0.49pa0.43
Gasholder decommissioningWe are in the process of decommissioning the region’s 44 gas holders. These holders are a legacy of a different age and are no longer needed due to improvements in our network. We aim to demolish them all over a 16 year period. We completed the decommissioning of 24 holders throughout RIIO GD1, and have exceeded our eight year target.23 by the end of RIIO GD11

Year: 2014/15

Loss of Supply

SummaryTargetActual
Number of planned interruptionsInterruptions to the gas supply for which customers were given prior notice (e.g. by letter). Planned mains replacement work is the most common scenario here. The stats show that the number of planned interruptions was less than our target for the year. We also comfortably beat our eight year target of 517,170 planned interruptions.64,64657,434
Number of unplanned interruptionsInterruptions to the gas supply caused by unplanned issues – such as gas leaks, or water finding its way into the pipe network. We finished RIIO GD1, comfortably ahead of our 8 year target of 103,677.12,96013,034

Repair

SummaryTargetActual
Annual riskWe work out a total risk score for all pipes which require a repair. The score is based on a wide range of criteria, and is helpful in allowing us to prioritise our repair work. Our focus on repairing more challenging pipes during the pandemic helped us to comfortably beat our risk target in the final year of RIIO GD1, consistent with our outperformance every year since 2013.<34.5m24.8m
Amount of repairs completed within 12 hoursThis refers to emergency repairs on our network. We were comfortably ahead of our target throughout RIIO GD1.62.50%62.9%

Network Capacity

SummaryTargetActual
Meeting NGN's 1 in 20 planning standard (MWh pa)This output requires our network to have enough capacity to ensure customers’ gas supplies are not interrupted during periods of highest demand (known as a one in 20 year event). Estimates of peak demand have actually been falling since 2005, and we have met our annual target throughout much of RIIO GD1.499,186502,916
PRI utilisation and capacityPressure Reduction Installations (PRI) reduce the pressure of gas before it is distributed to homes and businesses. To meet our obligations, assets need to be technically compliant and able to meet required volumes. We fell behind our target during the final year of RIIO GD1 due to a number of factors outside of our control, however overall our performance throughout the eight year period was on track.Phased planOn track

Network Reliability, maintaining operational performance

SummaryTargetActual
Percentage by volume of network meter errorsWe are responsible for monitoring and reporting the accuracy of the meters we use to measure the movement of gas from the National Transmission System into our network. We consistently met our annual target throughout RIIO GD1.<0.1% pa<0.2%
Number and duration of telemetered faultsThis target covers our response to telemetry faults (i.e. faults on equipment used to measure and record key data) on our above ground assets. We hit our target year on year throughout RIIO GD1.12063
Pressure System Safety Regulation FaultsStatutory inspections are carried out on our network. We hit our target year on year throughout RIIO GD1.0.49pa0.26
Gasholder decommissioningWe are in the process of decommissioning the region’s 44 gas holders. These holders are a legacy of a different age and are no longer needed due to improvements in our network. We aim to demolish them all over a 16 year period. We completed the decommissioning of 24 holders throughout RIIO GD1, and have exceeded our eight year target.23 by the end of RIIO GD12

Year: 2015/16

Loss of Supply

SummaryTargetActual
Number of planned interruptionsInterruptions to the gas supply for which customers were given prior notice (e.g. by letter). Planned mains replacement work is the most common scenario here. The stats show that the number of planned interruptions was less than our target for the year. We also comfortably beat our eight year target of 517,170 planned interruptions.64,64658,925
Number of unplanned interruptionsInterruptions to the gas supply caused by unplanned issues – such as gas leaks, or water finding its way into the pipe network. We finished RIIO GD1, comfortably ahead of our 8 year target of 103,677.12,96012,859

Repair

SummaryTargetActual
Annual riskWe work out a total risk score for all pipes which require a repair. The score is based on a wide range of criteria, and is helpful in allowing us to prioritise our repair work. Our focus on repairing more challenging pipes during the pandemic helped us to comfortably beat our risk target in the final year of RIIO GD1, consistent with our outperformance every year since 2013.<34.5m18.6m
Amount of repairs completed within 12 hoursThis refers to emergency repairs on our network. We were comfortably ahead of our target throughout RIIO GD1.62.50%64.4%

Network Capacity

SummaryTargetActual
Meeting NGN's 1 in 20 planning standard (MWh pa)This output requires our network to have enough capacity to ensure customers’ gas supplies are not interrupted during periods of highest demand (known as a one in 20 year event). Estimates of peak demand have actually been falling since 2005, and we have met our annual target throughout much of RIIO GD1.499,186492,560
PRI utilisation and capacityPressure Reduction Installations (PRI) reduce the pressure of gas before it is distributed to homes and businesses. To meet our obligations, assets need to be technically compliant and able to meet required volumes. We fell behind our target during the final year of RIIO GD1 due to a number of factors outside of our control, however overall our performance throughout the eight year period was on track.Phased planOn track

Network Reliability, maintaining operational performance

SummaryTargetActual
Percentage by volume of network meter errorsWe are responsible for monitoring and reporting the accuracy of the meters we use to measure the movement of gas from the National Transmission System into our network. We consistently met our annual target throughout RIIO GD1.<0.1% pa<0.0%
Number and duration of telemetered faultsThis target covers our response to telemetry faults (i.e. faults on equipment used to measure and record key data) on our above ground assets. We hit our target year on year throughout RIIO GD1.120135
Pressure System Safety Regulation FaultsStatutory inspections are carried out on our network. We hit our target year on year throughout RIIO GD1.0.49pa0.31
Gasholder decommissioningWe are in the process of decommissioning the region’s 44 gas holders. These holders are a legacy of a different age and are no longer needed due to improvements in our network. We aim to demolish them all over a 16 year period. We completed the decommissioning of 24 holders throughout RIIO GD1, and have exceeded our eight year target.23 by the end of RIIO GD13

Year: 2016/17

Loss of Supply

SummaryTargetActual
Number of planned interruptionsInterruptions to the gas supply for which customers were given prior notice (e.g. by letter). Planned mains replacement work is the most common scenario here. The stats show that the number of planned interruptions was less than our target for the year. We also comfortably beat our eight year target of 517,170 planned interruptions.64,64661,191
Number of unplanned interruptionsInterruptions to the gas supply caused by unplanned issues – such as gas leaks, or water finding its way into the pipe network. We finished RIIO GD1, comfortably ahead of our 8 year target of 103,677.12,96012,427

Repair

SummaryTargetActual
Annual riskWe work out a total risk score for all pipes which require a repair. The score is based on a wide range of criteria, and is helpful in allowing us to prioritise our repair work. Our focus on repairing more challenging pipes during the pandemic helped us to comfortably beat our risk target in the final year of RIIO GD1, consistent with our outperformance every year since 2013.<34.5m17.4m
Amount of repairs completed within 12 hoursThis refers to emergency repairs on our network. We were comfortably ahead of our target throughout RIIO GD1.62.50%62.3%

Network Capacity

SummaryTargetActual
Meeting NGN's 1 in 20 planning standard (MWh pa)This output requires our network to have enough capacity to ensure customers’ gas supplies are not interrupted during periods of highest demand (known as a one in 20 year event). Estimates of peak demand have actually been falling since 2005, and we have met our annual target throughout much of RIIO GD1.499,186476,850
PRI utilisation and capacityPressure Reduction Installations (PRI) reduce the pressure of gas before it is distributed to homes and businesses. To meet our obligations, assets need to be technically compliant and able to meet required volumes. We fell behind our target during the final year of RIIO GD1 due to a number of factors outside of our control, however overall our performance throughout the eight year period was on track.Phased planOn track

Network Reliability, maintaining operational performance

SummaryTargetActual
Percentage by volume of network meter errorsWe are responsible for monitoring and reporting the accuracy of the meters we use to measure the movement of gas from the National Transmission System into our network. We consistently met our annual target throughout RIIO GD1.<0.1% pa0.0%
Number and duration of telemetered faultsThis target covers our response to telemetry faults (i.e. faults on equipment used to measure and record key data) on our above ground assets. We hit our target year on year throughout RIIO GD1.12063
Pressure System Safety Regulation FaultsStatutory inspections are carried out on our network. We hit our target year on year throughout RIIO GD1.0.49pa0.35
Gasholder decommissioningWe are in the process of decommissioning the region’s 44 gas holders. These holders are a legacy of a different age and are no longer needed due to improvements in our network. We aim to demolish them all over a 16 year period. We completed the decommissioning of 24 holders throughout RIIO GD1, and have exceeded our eight year target.23 by the end of RIIO GD17

Year: 2017/18

Loss of Supply

SummaryTargetActual
Number of planned interruptionsInterruptions to the gas supply for which customers were given prior notice (e.g. by letter). Planned mains replacement work is the most common scenario here. The stats show that the number of planned interruptions was less than our target for the year. We also comfortably beat our eight year target of 517,170 planned interruptions.64,64662,669
Number of unplanned interruptionsInterruptions to the gas supply caused by unplanned issues – such as gas leaks, or water finding its way into the pipe network. We finished RIIO GD1, comfortably ahead of our 8 year target of 103,677.12,96013,714

Repair

SummaryTargetActual
Annual riskWe work out a total risk score for all pipes which require a repair. The score is based on a wide range of criteria, and is helpful in allowing us to prioritise our repair work. Our focus on repairing more challenging pipes during the pandemic helped us to comfortably beat our risk target in the final year of RIIO GD1, consistent with our outperformance every year since 2013.<34.5m19.3m
Amount of repairs completed within 12 hoursThis refers to emergency repairs on our network. We were comfortably ahead of our target throughout RIIO GD1.62.50%66.1%

Network Capacity

SummaryTargetActual
Meeting NGN's 1 in 20 planning standard (MWh pa)This output requires our network to have enough capacity to ensure customers’ gas supplies are not interrupted during periods of highest demand (known as a one in 20 year event). Estimates of peak demand have actually been falling since 2005, and we have met our annual target throughout much of RIIO GD1.499,186478,846
PRI utilisation and capacityPressure Reduction Installations (PRI) reduce the pressure of gas before it is distributed to homes and businesses. To meet our obligations, assets need to be technically compliant and able to meet required volumes. We fell behind our target during the final year of RIIO GD1 due to a number of factors outside of our control, however overall our performance throughout the eight year period was on track.Phased planOn track

Network Reliability, maintaining operational performance

SummaryTargetActual
Percentage by volume of network meter errorsWe are responsible for monitoring and reporting the accuracy of the meters we use to measure the movement of gas from the National Transmission System into our network. We consistently met our annual target throughout RIIO GD1.<0.1% pa0.0%
Number and duration of telemetered faultsThis target covers our response to telemetry faults (i.e. faults on equipment used to measure and record key data) on our above ground assets. We hit our target year on year throughout RIIO GD1.12095
Pressure System Safety Regulation FaultsStatutory inspections are carried out on our network. We hit our target year on year throughout RIIO GD1.0.49pa0.37
Gasholder decommissioningWe are in the process of decommissioning the region’s 44 gas holders. These holders are a legacy of a different age and are no longer needed due to improvements in our network. We aim to demolish them all over a 16 year period. We completed the decommissioning of 24 holders throughout RIIO GD1, and have exceeded our eight year target.23 by the end of RIIO GD13

Year: 2018/19

Loss of Supply

SummaryTargetActual
Number of planned interruptionsInterruptions to the gas supply for which customers were given prior notice (e.g. by letter). Planned mains replacement work is the most common scenario here. The stats show that the number of planned interruptions was less than our target for the year. We also comfortably beat our eight year target of 517,170 planned interruptions.64,64663,774
Number of unplanned interruptionsInterruptions to the gas supply caused by unplanned issues – such as gas leaks, or water finding its way into the pipe network. We finished RIIO GD1, comfortably ahead of our 8 year target of 103,677.12,96014,030

Repair

SummaryTargetActual
Annual riskWe work out a total risk score for all pipes which require a repair. The score is based on a wide range of criteria, and is helpful in allowing us to prioritise our repair work. Our focus on repairing more challenging pipes during the pandemic helped us to comfortably beat our risk target in the final year of RIIO GD1, consistent with our outperformance every year since 2013.<34.5m23.6m
Amount of repairs completed within 12 hoursThis refers to emergency repairs on our network. We were comfortably ahead of our target throughout RIIO GD1.62.50%68.4%

Network Capacity

SummaryTargetActual
Meeting NGN's 1 in 20 planning standard (MWh pa)This output requires our network to have enough capacity to ensure customers’ gas supplies are not interrupted during periods of highest demand (known as a one in 20 year event). Estimates of peak demand have actually been falling since 2005, and we have met our annual target throughout much of RIIO GD1.499,186478,846
PRI utilisation and capacityPressure Reduction Installations (PRI) reduce the pressure of gas before it is distributed to homes and businesses. To meet our obligations, assets need to be technically compliant and able to meet required volumes. We fell behind our target during the final year of RIIO GD1 due to a number of factors outside of our control, however overall our performance throughout the eight year period was on track.Phased planOn track

Network Reliability, maintaining operational performance

SummaryTargetActual
Percentage by volume of network meter errorsWe are responsible for monitoring and reporting the accuracy of the meters we use to measure the movement of gas from the National Transmission System into our network. We consistently met our annual target throughout RIIO GD1.<0.1% pa0.1%
Number and duration of telemetered faultsThis target covers our response to telemetry faults (i.e. faults on equipment used to measure and record key data) on our above ground assets. We hit our target year on year throughout RIIO GD1.120116
Pressure System Safety Regulation FaultsStatutory inspections are carried out on our network. We hit our target year on year throughout RIIO GD1.0.49pa0.29
Gasholder decommissioningWe are in the process of decommissioning the region’s 44 gas holders. These holders are a legacy of a different age and are no longer needed due to improvements in our network. We aim to demolish them all over a 16 year period. We completed the decommissioning of 24 holders throughout RIIO GD1, and have exceeded our eight year target.23 by the end of RIIO GD13

Year: 2019/20

Loss of Supply

SummaryTargetActual
Number of planned interruptionsInterruptions to the gas supply for which customers were given prior notice (e.g. by letter). Planned mains replacement work is the most common scenario here. The stats show that the number of planned interruptions was less than our target for the year. We also comfortably beat our eight year target of 517,170 planned interruptions.64,64650,413
Number of unplanned interruptionsInterruptions to the gas supply caused by unplanned issues – such as gas leaks, or water finding its way into the pipe network. We finished RIIO GD1, comfortably ahead of our 8 year target of 103,677.12,96012,110

Repair

SummaryTargetActual
Annual riskWe work out a total risk score for all pipes which require a repair. The score is based on a wide range of criteria, and is helpful in allowing us to prioritise our repair work. Our focus on repairing more challenging pipes during the pandemic helped us to comfortably beat our risk target in the final year of RIIO GD1, consistent with our outperformance every year since 2013.<34.5m23.0m
Amount of repairs completed within 12 hoursThis refers to emergency repairs on our network. We were comfortably ahead of our target throughout RIIO GD1.62.50%64.3%

Network Capacity

SummaryTargetActual
Meeting NGN's 1 in 20 planning standard (MWh pa)This output requires our network to have enough capacity to ensure customers’ gas supplies are not interrupted during periods of highest demand (known as a one in 20 year event). Estimates of peak demand have actually been falling since 2005, and we have met our annual target throughout much of RIIO GD1.499,186473,411
PRI utilisation and capacityPressure Reduction Installations (PRI) reduce the pressure of gas before it is distributed to homes and businesses. To meet our obligations, assets need to be technically compliant and able to meet required volumes. We fell behind our target during the final year of RIIO GD1 due to a number of factors outside of our control, however overall our performance throughout the eight year period was on track.Phased planOn track

Network Reliability, maintaining operational performance

SummaryTargetActual
Percentage by volume of network meter errorsWe are responsible for monitoring and reporting the accuracy of the meters we use to measure the movement of gas from the National Transmission System into our network. We consistently met our annual target throughout RIIO GD1.<0.1% pa0.0%
Number and duration of telemetered faultsThis target covers our response to telemetry faults (i.e. faults on equipment used to measure and record key data) on our above ground assets. We hit our target year on year throughout RIIO GD1.12094
Pressure System Safety Regulation FaultsStatutory inspections are carried out on our network. We hit our target year on year throughout RIIO GD1.0.49pa0.19
Gasholder decommissioningWe are in the process of decommissioning the region’s 44 gas holders. These holders are a legacy of a different age and are no longer needed due to improvements in our network. We aim to demolish them all over a 16 year period. We completed the decommissioning of 24 holders throughout RIIO GD1, and have exceeded our eight year target.23 by the end of RIIO GD11

Year: 2020/21

Loss of Supply

SummaryTargetActual
Number of planned interruptionsInterruptions to the gas supply for which customers were given prior notice (e.g. by letter). Planned mains replacement work is the most common scenario here. The stats show that the number of planned interruptions was less than our target for the year. We also comfortably beat our eight year target of 517,170 planned interruptions.64,64621,464
Number of unplanned interruptionsInterruptions to the gas supply caused by unplanned issues – such as gas leaks, or water finding its way into the pipe network. We finished RIIO GD1, comfortably ahead of our 8 year target of 103,677.12,96010,265

Repair

SummaryTargetActual
Annual riskWe work out a total risk score for all pipes which require a repair. The score is based on a wide range of criteria, and is helpful in allowing us to prioritise our repair work. Our focus on repairing more challenging pipes during the pandemic helped us to comfortably beat our risk target in the final year of RIIO GD1, consistent with our outperformance every year since 2013.<34.5m12.5m
Amount of repairs completed within 12 hoursThis refers to emergency repairs on our network. We were comfortably ahead of our target throughout RIIO GD1.62.50%65.1%

Network Capacity

SummaryTargetActual
Meeting NGN's 1 in 20 planning standard (MWh pa)This output requires our network to have enough capacity to ensure customers’ gas supplies are not interrupted during periods of highest demand (known as a one in 20 year event). Estimates of peak demand have actually been falling since 2005, and we have met our annual target throughout much of RIIO GD1.499,186485,014
PRI utilisation and capacityPressure Reduction Installations (PRI) reduce the pressure of gas before it is distributed to homes and businesses. To meet our obligations, assets need to be technically compliant and able to meet required volumes. We fell behind our target during the final year of RIIO GD1 due to a number of factors outside of our control, however overall our performance throughout the eight year period was on track.Phased planOn track

Network Reliability, maintaining operational performance

SummaryTargetActual
Percentage by volume of network meter errorsWe are responsible for monitoring and reporting the accuracy of the meters we use to measure the movement of gas from the National Transmission System into our network. We consistently met our annual target throughout RIIO GD1.<0.1% pa0.1%
Number and duration of telemetered faultsThis target covers our response to telemetry faults (i.e. faults on equipment used to measure and record key data) on our above ground assets. We hit our target year on year throughout RIIO GD1.12089
Pressure System Safety Regulation FaultsStatutory inspections are carried out on our network. We hit our target year on year throughout RIIO GD1.0.49pa0.41
Gasholder decommissioningWe are in the process of decommissioning the region’s 44 gas holders. These holders are a legacy of a different age and are no longer needed due to improvements in our network. We aim to demolish them all over a 16 year period. We completed the decommissioning of 24 holders throughout RIIO GD1, and have exceeded our eight year target.23 by the end of RIIO GD14

Investing for a thriving environment

Keeping 2.9 million homes and businesses cooking on gas is a resource intensive business. It’s our responsibility to reduce our day-to-day carbon footprint, while helping green, alternative fuels to flourish.

  • 2013/14
  • 2014/15
  • 2015/16
  • 2016/17
  • 2017/18
  • 2018/19
  • 2019/20
  • 2020/21

Year: 2013/14

Environmental emissions

SummaryTargetActual
Shrinkage (GWh)Shrinkage comprises gas leakage, gas illegally taken by third parties and own use gas by NGN, primarily used for pre-heating gas at locations where gas transfers from one pressure tier to another.
459 GWh417 GWh
Leakage (GWh)Gas leakage from the network.
434 GWh395 GWh
Business carbon footprint (tCO2e)
Total Scopes 1, 2 and 3 (location-based) emissions excluding shrinkage.
No specific RIIO-GD1 target
21,739 tC02-e

Other environmental measures

SummaryTargetActual
Number of sites where statutory remediation has been carried out
Number of sites where environmental remediation was carried out to return the land to a statutory compliant condition.No specific RIIO-GD1 target0
Use of virgin aggregate (tonnes)The use of newly quarried (primary) natural materials, such as gravel or crushed stone, as opposed to recycled (secondary) aggregate, to reinstate excavations following mains replacement and repair work.<17,000 t37,862 t
Amount of spoil to landfill (tonnes)Waste generated by utility works excavations (for example in the road) that is not reused or recycled and is disposed of at a permitted/licensed landfill.<13,000 t61,555 t
ISO 14001 major non conformitiesSignificant incidences of the environmental management system not meeting the requirements of the ISO14001 standard.No specific RIIO-GD1 target0

Biomethane

SummaryTargetActual
Total capacity of biomethane connected (Standard Cubic Metres per Hour (SCMH))Capacity of biomethane connected during the reporting year.No target0 SCMH
Total capacity of biomethane enquiries/applications in progress (Standard Cubic Metres per Hour (SCMH))Capacity represented by biomethane enquiries/applications in progress in year.No target11,800 SCMH
Information provision and connection charging for distributed gasThe provision of information on the connection process and associated charges to customers seeking to inject distributed gas, such as biomethane, directly into the gas distribution network.No targetMet
Voluntary standards of service: 15 day response to initial enquiry under 7barThe percentage of initial enquiries for distributed gas connections below 7 bar that receive a response within 15 working days.100%100%
Voluntary standard of service: 30 day response to capacity study under 7 barThe percentage of capacity studies for connections below 7 bar that receive a response within 30 working days.100%100%

Year: 2014/15

Environmental emissions

SummaryTargetActual
Shrinkage (GWh)Shrinkage comprises gas leakage, gas illegally taken by third parties and own use gas by NGN, primarily used for pre-heating gas at locations where gas transfers from one pressure tier to another.
445 GWh397 GWh
Leakage (GWh)Gas leakage from the network.
420 GWh375 GWh
Business carbon footprint (tCO2e)
Total Scopes 1, 2 and 3 (location-based) emissions excluding shrinkage.
No specific RIIO-GD1 target
25,542 tC02-e

Other environmental measures

SummaryTargetActual
Number of sites where statutory remediation has been carried outNumber of sites where environmental remediation was carried out to return the land to a statutory compliant condition.No specific RIIO-GD1 target0
Use of virgin aggregate (tonnes)The use of newly quarried (primary) natural materials, such as gravel or crushed stone, as opposed to recycled (secondary) aggregate, to reinstate excavations following mains replacement and repair work.<17,000 t29,426 t
Amount of spoil to landfill (tonnes)Waste generated by utility works excavations (for example in the road) that is not reused or recycled and is disposed of at a permitted/licensed landfill.<13,000 t18,565 t
ISO 14001 major non conformitiesSignificant incidences of the environmental management system not meeting the requirements of the ISO14001 standard.No specific RIIO-GD1 target0

Biomethane

SummaryTargetActual
Total capacity of biomethane connected (Standard Cubic Metres per Hour (SCMH))Capacity of biomethane connected during the reporting year.No target1,200 SCMH
Total capacity of biomethane enquiries/applications in progress (Standard Cubic Metres per Hour (SCMH))Capacity represented by biomethane enquiries/applications in progress in year.No target29,600 SCMH
Information provision and connection charging for distributed gasThe provision of information on the connection process and associated charges to customers seeking to inject distributed gas, such as biomethane, directly into the gas distribution network.No targetMet
Voluntary standards of service: 15 day response to initial enquiry under 7barThe percentage of initial enquiries for distributed gas connections below 7 bar that receive a response within 15 working days.100%98%
Voluntary standard of service: 30 day response to capacity study under 7 barThe percentage of capacity studies for connections below 7 bar that receive a response within 30 working days.100%100%

Year: 2015/16

Environmental emissions

SummaryTargetActual
Shrinkage (GWh)Shrinkage comprises gas leakage, gas illegally taken by third parties and own use gas by NGN, primarily used for pre-heating gas at locations where gas transfers from one pressure tier to another.
433 GWh382 GWh
Leakage (GWh)Gas leakage from the network.
408 GWh360 GWh
Business carbon footprint (tCO2e)
Total Scopes 1, 2 and 3 (location-based) emissions excluding shrinkage.
No specific RIIO-GD1 target
23,763 tCO2e

Other environmental measures

SummaryTargetActual
Number of sites where statutory remediation has been carried outNumber of sites where environmental remediation was carried out to return the land to a statutory compliant condition.No specific RIIO-GD1 target3
Use of virgin aggregate (tonnes)The use of newly quarried (primary) natural materials, such as gravel or crushed stone, as opposed to recycled (secondary) aggregate, to reinstate excavations following mains replacement and repair work.<17,000 t33,553 t
Amount of spoil to landfill (tonnes)Waste generated by utility works excavations (for example in the road) that is not reused or recycled and is disposed of at a permitted/licensed landfill.<13,000 t17,311 t
ISO 14001 major non conformitiesSignificant incidences of the environmental management system not meeting the requirements of the ISO14001 standard.No specific RIIO-GD1 target0

Biomethane

SummaryTargetActual
Total capacity of biomethane connected (Standard Cubic Metres per Hour (SCMH))Capacity of biomethane connected during the reporting year.No target7,800 SCMH
Total capacity of biomethane enquiries/applications in progress (Standard Cubic Metres per Hour (SCMH))Capacity represented by biomethane enquiries/applications in progress in year.No target27,390 SCMH
Information provision and connection charging for distributed gasThe provision of information on the connection process and associated charges to customers seeking to inject distributed gas, such as biomethane, directly into the gas distribution network.No targetMet
Voluntary standards of service: 15 day response to initial enquiry under 7barThe percentage of initial enquiries for distributed gas connections below 7 bar that receive a response within 15 working days.100%89%
Voluntary standard of service: 30 day response to capacity study under 7 barThe percentage of capacity studies for connections below 7 bar that receive a response within 30 working days.100%100%

Year: 2016/17

Environmental emissions

SummaryTargetActual
Shrinkage (GWh)Shrinkage comprises gas leakage, gas illegally taken by third parties and own use gas by NGN, primarily used for pre-heating gas at locations where gas transfers from one pressure tier to another.
423 GWh354 GWh
Leakage (GWh)Gas leakage from the network.
398 GWh
332 GWh
Business carbon footprintTotal Scopes 1, 2 and 3 (location-based) emissions excluding shrinkage.
No specific RIIO-GD1 target
21,135 tCO2e

Other environmental measures

SummaryTargetActual
Number of sites where statutory remediation has been carried outNumber of sites where environmental remediation was carried out to return the land to a statutory compliant condition.No specific RIIO-GD1 target3
Use of virgin aggregate (tonnes)The use of newly quarried (primary) natural materials, such as gravel or crushed stone, as opposed to recycled (secondary) aggregate, to reinstate excavations following mains replacement and repair work.<17,000 t17,140 t
Amount of spoil to landfill (tonnes)Waste generated by utility works excavations (for example in the road) that is not reused or recycled and is disposed of at a permitted/licensed landfill.<13,000 t6,232 t
ISO 14001 major non conformitiesSignificant incidences of the environmental management system not meeting the requirements of the ISO14001 standard.No specific RIIO-GD1 target0

Biomethane

SummaryTargetActual
Total capacity of biomethane connected (Standard Cubic Metres per Hour (SCMH))Capacity of biomethane connected during the reporting year.No target500 SCMH
Total capacity of biomethane enquiries/applications in progress (Standard Cubic Metres per Hour (SCMH))Capacity represented by biomethane enquiries/applications in progress in year.No target38,440 SCMH
Information provision and connection charging for distributed gasThe provision of information on the connection process and associated charges to customers seeking to inject distributed gas, such as biomethane, directly into the gas distribution network.No targetMet
Voluntary standards of service: 15 day response to initial enquiry under 7barThe percentage of initial enquiries for distributed gas connections below 7 bar that receive a response within 15 working days.100%100%
Voluntary standard of service: 30 day response to capacity study under 7 barThe percentage of capacity studies for connections below 7 bar that receive a response within 30 working days.100%100%

Year: 2017/18

Environmental emissions

SummaryTargetActual
Shrinkage (GWh)Shrinkage comprises gas leakage, gas illegally taken by third parties and own use gas by NGN, primarily used for pre-heating gas at locations where gas transfers from one pressure tier to another.
412 GWh352 GWh
Leakage (GWh)Gas leakage from the network.
386 GWh
329 GWh
Business carbon footprint (tCO2e)
Total Scopes 1, 2 and 3 (location-based) emissions excluding shrinkage.
No specific RIIO-GD1 target
21,827 tCO2e

Other environmental measures

SummaryTargetActual
Number of sites where statutory remediation has been carried outNumber of sites where environmental remediation was carried out to return the land to a statutory compliant condition.No specific RIIO-GD1 target3
Use of virgin aggregate (tonnes)The use of newly quarried (primary) natural materials, such as gravel or crushed stone, as opposed to recycled (secondary) aggregate, to reinstate excavations following mains replacement and repair work.<17,000 t14,321 t
Amount of spoil to landfill (tonnes)Waste generated by utility works excavations (for example in the road) that is not reused or recycled and is disposed of at a permitted/licensed landfill.<13,000 t308 t
ISO 14001 major non conformitiesSignificant incidences of the environmental management system not meeting the requirements of the ISO14001 standard.No specific RIIO-GD1 target0

Biomethane

SummaryTargetActual
Total capacity of biomethane connected (Standard Cubic Metres per Hour (SCMH))Capacity of biomethane connected during the reporting year.No target550 SCMH
Total capacity of biomethane enquiries/applications in progress (Standard Cubic Metres per Hour (SCMH))Capacity represented by biomethane enquiries/applications in progress in year.No target18,740 SCMH
Information provision and connection charging for distributed gasThe provision of information on the connection process and associated charges to customers seeking to inject distributed gas, such as biomethane, directly into the gas distribution network.No targetMet
Voluntary standards of service: 15 day response to initial enquiry under 7barThe percentage of initial enquiries for distributed gas connections below 7 bar that receive a response within 15 working days.100%100%
Voluntary standard of service: 30 day response to capacity study under 7 barThe percentage of capacity studies for connections below 7 bar that receive a response within 30 working days.100%100%

Year: 2018/19

Environmental emissions

SummaryTargetActual
Shrinkage (GWh)
Shrinkage comprises gas leakage, gas illegally taken by third parties and own use gas by NGN, primarily used for pre-heating gas at locations where gas transfers from one pressure tier to another.
401 GWh
341 GWh
Leakage (GWh)
Gas leakage from the network.
376 GWh319 GWh
Business carbon footprint (tCO2e)
Total Scopes 1, 2 and 3 (location-based) emissions excluding shrinkage.
No specific RIIO-GD1 target
21,832 tCO2e

Other environmental measures

SummaryTargetActual
Number of sites where statutory remediation has been carried outNumber of sites where environmental remediation was carried out to return the land to a statutory compliant condition.No specific RIIO-GD1 target3
Use of virgin aggregate (tonnes)The use of newly quarried (primary) natural materials, such as gravel or crushed stone, as opposed to recycled (secondary) aggregate, to reinstate excavations following mains replacement and repair work.<17,000 t8,160 t
Amount of spoil to landfill (tonnes)Waste generated by utility works excavations (for example in the road) that is not reused or recycled and is disposed of at a permitted/licensed landfill.<13,000 t744 t
ISO 14001 major non conformitiesSignificant incidences of the environmental management system not meeting the requirements of the ISO14001 standard.No specific RIIO-GD1 target0

Biomethane

SummaryTargetActual
Total capacity of biomethane connected (Standard Cubic Metres per Hour (SCMH))Capacity of biomethane connected during the reporting year.No target0 SCMH
Total capacity of biomethane enquiries/applications in progress (Standard Cubic Metres per Hour (SCMH))Capacity represented by biomethane enquiries/applications in progress in year.No target9,190 SCMH
Information provision and connection charging for distributed gasThe provision of information on the connection process and associated charges to customers seeking to inject distributed gas, such as biomethane, directly into the gas distribution network.No targetMet
Voluntary standards of service: 15 day response to initial enquiry under 7barThe percentage of initial enquiries for distributed gas connections below 7 bar that receive a response within 15 working days.100%100%
Voluntary standard of service: 30 day response to capacity study under 7 barThe percentage of capacity studies for connections below 7 bar that receive a response within 30 working days.100%100%

Year: 2019/20

Environmental emissions

SummaryTargetActual
Shrinkage (GWh)
Shrinkage comprises gas leakage, gas illegally taken by third parties and own use gas by NGN, primarily used for pre-heating gas at locations where gas transfers from one pressure tier to another.
390 GWh
328 GWh
Leakage (GWh)
Gas leakage from the network.
364 GWh
306 GWh
Business carbon footprint (tCO2e)
Total Scopes 1, 2 and 3 (location-based) emissions excluding shrinkage.
No specific RIIO-GD1 target
22,294 tCO2e

Other environmental measures

SummaryTargetActual
Number of sites where statutory remediation has been carried outNumber of sites where environmental remediation was carried out to return the land to a statutory compliant condition.No specific RIIO-GD1 target2
Use of virgin aggregate (tonnes)The use of newly quarried (primary) natural materials, such as gravel or crushed stone, as opposed to recycled (secondary) aggregate, to reinstate excavations following mains replacement and repair work.<17,000 t13,505 t
Amount of spoil to landfill (tonnes)Waste generated by utility works excavations (for example in the road) that is not reused or recycled and is disposed of at a permitted/licensed landfill.<13,000 t120 t
ISO 14001 major non conformitiesSignificant incidences of the environmental management system not meeting the requirements of the ISO14001 standard.No specific RIIO-GD1 target0

Biomethane

SummaryTargetActual
Total capacity of biomethane connected (Standard Cubic Metres per Hour (SCMH))Capacity of biomethane connected during the reporting year.No target6,290 SCMH
Total capacity of biomethane enquiries/applications in progress (Standard Cubic Metres per Hour (SCMH))Capacity represented by biomethane enquiries/applications in progress in year.No target9,170 SCMH
Information provision and connection charging for distributed gasThe provision of information on the connection process and associated charges to customers seeking to inject distributed gas, such as biomethane, directly into the gas distribution network.No targetMet
Voluntary standards of service: 15 day response to initial enquiry under 7barThe percentage of initial enquiries for distributed gas connections below 7 bar that receive a response within 15 working days.100%100%
Voluntary standard of service: 30 day response to capacity study under 7 barThe percentage of capacity studies for connections below 7 bar that receive a response within 30 working days.100%100%

Year: 2020/21

Environmental emissions

SummaryTargetActual
Shrinkage (GWh)
Shrinkage comprises gas leakage, gas illegally taken by third parties and own use gas by NGN, primarily used for pre-heating gas at locations where gas transfers from one pressure tier to another.
379 GWh
319 GWh
Leakage (GWh)
Gas leakage from the network.
354 GWh
297 GWh
Business carbon footprint (tCO2e)
Total Scopes 1, 2 and 3 (location-based) emissions excluding shrinkage.
No specific RIIO-GD1 target
20,687 tCO2e

Other environmental measures

SummaryTargetActual
Number of sites where statutory remediation has been carried outNumber of sites where environmental remediation was carried out to return the land to a statutory compliant condition.No specific RIIO-GD1 target2
Use of virgin aggregate (tonnes)The use of newly quarried (primary) natural materials, such as gravel or crushed stone, as opposed to recycled (secondary) aggregate, to reinstate excavations following mains replacement and repair work.<17,000 t14,740 t
Amount of spoil to landfill (tonnes)Waste generated by utility works excavations (for example in the road) that is not reused or recycled and is disposed of at a permitted/licensed landfill.<13,000 t202 t
ISO 14001 major non conformitiesSignificant incidences of the environmental management system not meeting the requirements of the ISO14001 standard.No specific RIIO-GD1 target0

Biomethane

SummaryTargetActual
Total capacity of biomethane connected (Standard Cubic Metres per Hour (SCMH))Capacity of biomethane connected during the reporting year.No target0 SCMH
Total capacity of biomethane enquiries/applications in progress (Standard Cubic Metres per Hour (SCMH))Capacity represented by biomethane enquiries/applications in progress in year.No target7,446 SCMH
Information provision and connection charging for distributed gasThe provision of information on the connection process and associated charges to customers seeking to inject distributed gas, such as biomethane, directly into the gas distribution network.No targetMet
Voluntary standards of service: 15 day response to initial enquiry under 7barThe percentage of initial enquiries for distributed gas connections below 7 bar that receive a response within 15 working days.100%100%
Voluntary standard of service: 30 day response to capacity study under 7 barThe percentage of capacity studies for connections below 7 bar that receive a response within 30 working days.100%100%

Support where its needed most

Our region contains some of the most economically challenged communities in the UK, from remote parts of rural Northumberland to deprived areas of Bradford.

As a company that’s embedded in these neighbourhoods, it’s our duty to support communities and individuals facing difficulties, such as fuel poverty and associated forms of vulnerability.

Taking on the 'silent killer'

Carbon Monoxide (CO) is a poisonous gas produced by the incomplete burning of carbon fuels including solid fuels and liquid petroleum gas. (e.g. due to faulty boilers or other gas appliance) CO can’t be seen, smelt or tasted, and is often referred to as ‘the silent killer.’

CO poisoning claims around 40 lives each year in England and Wales.

We educated and protected the region against CO, through schools workshops; customer briefings in the home; public awareness campaigns and by equipping all our emergency engineers with handheld CO detectors.

We also worked closely with other gas distributors and charities on joint activity.

  • Year: 2013/14
  • Year: 2014/15
  • Year: 2015/16
  • Year: 2016/17
  • Year: 2017/18
  • Year: 2018/19
  • Year: 2019/20
  • Year: 2020/21

Year: Year: 2013/14

CO Detection Technology

SummaryTargetActual
Providing emergency engineers with smart CO detection technologyWe have completed our roll out of life saving CO detection equipment for our emergency gas engineers. 1,200 engineers now use this technology each day.200200

Year: Year: 2014/15

CO Detection Technology

SummaryTargetActual
Providing emergency engineers with smart CO detection technologyWe have completed our roll out of life saving CO detection equipment for our emergency gas engineers. 1,200 engineers now use this technology each day.200200

Year: Year: 2015/16

CO Detection Technology

SummaryTargetActual
Providing emergency engineers with smart CO detection technologyWe have completed our roll out of life saving CO detection equipment for our emergency gas engineers. 1,200 engineers now use this technology each day.200200

Year: Year: 2016/17

CO Detection Technology

SummaryTargetActual
Providing emergency engineers with smart CO detection technologyWe have completed our roll out of life saving CO detection equipment for our emergency gas engineers. 1,200 engineers now use this technology each day.200Business as usual

Year: Year: 2017/18

CO Detection Technology

SummaryTargetActual
Providing emergency engineers with smart CO detection technologyWe have completed our roll out of life saving CO detection equipment for our emergency gas engineers. 1,200 engineers now use this technology each day.200Business as usual

Year: Year: 2018/19

CO Detection Technology

SummaryTargetActual
Providing emergency engineers with smart CO detection technologyWe have completed our roll out of life saving CO detection equipment for our emergency gas engineers. 1,200 engineers now use this technology each day.200Business as usual

Year: Year: 2019/20

CO Detection Technology

SummaryTargetActual
Providing emergency engineers with smart CO detection technologyWe have completed our roll out of life saving CO detection equipment for our emergency gas engineers. 1,200 engineers now use this technology each day.200Business as usual

Year: Year: 2020/21

CO Detection Technology

SummaryTargetActual
Providing emergency engineers with smart CO detection technologyWe have completed our roll out of life saving CO detection equipment for our emergency gas engineers. 1,200 engineers now use this technology each day.200Business as usual

Staying warm and healthy

We’re committed to helping our more vulnerable customers stay warm; budget effectively and look after their health.

With fuel poverty still a pressing issue in our region and we provided a range of additional support such as free home energy audits, a funding scheme for grass roots initiatives and partnerships with charities and training providers.
We also continued to train our own colleagues, so that they can better advise customers who are facing vulnerable circumstances.

  • Year: 2013/14
  • Year: 2014/15
  • Year: 2015/16
  • Year: 2016/17
  • Year: 2017/18
  • Year: 2018/19
  • Year: 2019/20
  • Year: 2020/21

Year: Year: 2013/14

Fuel Poor Connections

SummaryTargetActual
Number of fuel poor connectionsWe exceeded our target for providing gas connections to some of our poorest customers, delivering 15,621 free gas connections since 2013/14 – smashing our eight year target of 14,000!1,9171,164

Year: Year: 2014/15

Fuel Poor Connections

SummaryTargetActual
Number of fuel poor connectionsWe exceeded our target for providing gas connections to some of our poorest customers, delivering 15,621 free gas connections since 2013/14 – smashing our eight year target of 14,000!1,9171,707

Year: Year: 2015/16

Fuel Poor Connections

SummaryTargetActual
Number of fuel poor connectionsWe exceeded our target for providing gas connections to some of our poorest customers, delivering 15,621 free gas connections since 2013/14 – smashing our eight year target of 14,000!1,9172,458

Year: Year: 2016/17

Fuel Poor Connections

SummaryTargetActual
Number of fuel poor connectionsWe exceeded our target for providing gas connections to some of our poorest customers, delivering 15,621 free gas connections since 2013/14 – smashing our eight year target of 14,000!1,9172,626

Year: Year: 2017/18

Fuel Poor Connections

SummaryTargetActual
Number of fuel poor connectionsWe exceeded our target for providing gas connections to some of our poorest customers, delivering 15,621 free gas connections since 2013/14 – smashing our eight year target of 14,000!1,9172,099

Year: Year: 2018/19

Fuel Poor Connections

SummaryTargetActual
Number of fuel poor connectionsWe exceeded our target for providing gas connections to some of our poorest customers, delivering 15,621 free gas connections since 2013/14 – smashing our eight year target of 14,000!1,9172,763

Year: Year: 2019/20

Fuel Poor Connections

SummaryTargetActual
Number of fuel poor connectionsWe exceeded our target for providing gas connections to some of our poorest customers, delivering 15,621 free gas connections since 2013/14 – smashing our eight year target of 14,000!1,9171,933

Year: Year: 2020/21

Fuel Poor Connections

SummaryTargetActual
Number of fuel poor connectionsWe exceeded our target for providing gas connections to some of our poorest customers, delivering 15,621 free gas connections since 2013/14 – smashing our eight year target of 14,000!1,917859

Delivering for our customers

We continued to listen to and understand our customers needs by working closely with them and our stakeholders to make sure we delivered a great service.

  • Year: 2013/14
  • Year: 2014/15
  • Year: 2015/2016
  • Year: 2016/17
  • Year: 2017/18
  • Year: 2018/19
  • Year: 2019/2020
  • Year: 2020/21

Year: Year: 2013/14

Customer Service

SummaryTargetActual
Unplanned interruptions (score out of 10)Unplanned interruptions are issues such as gas escapes, which result in the gas going of suddenly and without warning. Each year, Ofgem carries out surveys among a cross-section of customers affected by such an interruption, to gauge their level of satisfaction with our response. Our score of 9.55 is ahead of target, and in line with our outperformance throughout RIIO GD1. The professionalism and dedication of our emergency engineers had a lot to do with this great performance.9.09.3
Planned interruptions (score out of 10)Planned interruptions are periods when the gas goes off for essential repair or maintenance work. Customers are given advanced notice, usually through letters. Our score of 8.92 is ahead of target and in line with our outperformance throughout much of RIIO GD1. Lots of elements went into this strong performance, including the use of detailed mitigation plans for each job, to minimise inconvenience, and weighting our programme of work, so that fewer jobs are carried out in winter, when the impact of losing gas is more acute.8.58.4
Connections (score out of 10)This is a measure of how we performed when installing private gas connections for homes or businesses. Our score of 9.05 out of 10 is ahead of our target and in line with our outperformance throughout RIIO GD1. We’ve transformed our connections service in recent years, to make it far more customer focused, and this is reflected in the strong score.8.48.6
Complaints metricWe receive an overall complaints score each year, based on four different elements: the percentage of complaints unresolved after one working day; percentage of complaints unresolved after 31 working days; percentage of repeat complaints and the number of Energy Ombudsman decisions that have gone against us.11.64.8

Year: Year: 2014/15

Customer Service

SummaryTargetActual
Unplanned interruptions (score out of 10)Unplanned interruptions are issues such as gas escapes, which result in the gas going of suddenly and without warning. Each year, Ofgem carries out surveys among a cross-section of customers affected by such an interruption, to gauge their level of satisfaction with our response. Our score of 9.55 is ahead of target, and in line with our outperformance throughout RIIO GD1. The professionalism and dedication of our emergency engineers had a lot to do with this great performance.9.09.4
Planned interruptions (score out of 10)Planned interruptions are periods when the gas goes off for essential repair or maintenance work. Customers are given advanced notice, usually through letters. Our score of 8.92 is ahead of target and in line with our outperformance throughout much of RIIO GD1. Lots of elements went into this strong performance, including the use of detailed mitigation plans for each job, to minimise inconvenience, and weighting our programme of work, so that fewer jobs are carried out in winter, when the impact of losing gas is more acute.8.58.7
Connections (score out of 10)This is a measure of how we performed when installing private gas connections for homes or businesses. Our score of 9.05 out of 10 is ahead of our target and in line with our outperformance throughout RIIO GD1. We’ve transformed our connections service in recent years, to make it far more customer focused, and this is reflected in the strong score.8.49.0
Complaints metricWe receive an overall complaints score each year, based on four different elements: the percentage of complaints unresolved after one working day; percentage of complaints unresolved after 31 working days; percentage of repeat complaints and the number of Energy Ombudsman decisions that have gone against us.11.62.7

Year: Year: 2015/2016

Customer Service 2015/16

SummaryTargetActual
Unplanned interruptions (score out of 10)Unplanned interruptions are issues such as gas escapes, which result in the gas going of suddenly and without warning. Each year, Ofgem carries out surveys among a cross-section of customers affected by such an interruption, to gauge their level of satisfaction with our response. Our score of 9.55 is ahead of target, and in line with our outperformance throughout RIIO GD1. The professionalism and dedication of our emergency engineers had a lot to do with this great performance.9.09.5
Planned interruptions (score out of 10)Planned interruptions are periods when the gas goes off for essential repair or maintenance work. Customers are given advanced notice, usually through letters. Our score of 8.92 is ahead of target and in line with our outperformance throughout much of RIIO GD1. Lots of elements went into this strong performance, including the use of detailed mitigation plans for each job, to minimise inconvenience, and weighting our programme of work, so that fewer jobs are carried out in winter, when the impact of losing gas is more acute.8.58.9
Connections (score out of 10)This is a measure of how we performed when installing private gas connections for homes or businesses. Our score of 9.05 out of 10 is ahead of our target and in line with our outperformance throughout RIIO GD1. We’ve transformed our connections service in recent years, to make it far more customer focused, and this is reflected in the strong score.8.49.1
Complaints metricWe receive an overall complaints score each year, based on four different elements: the percentage of complaints unresolved after one working day; percentage of complaints unresolved after 31 working days; percentage of repeat complaints and the number of Energy Ombudsman decisions that have gone against us.11.63.1

Year: Year: 2016/17

Customer Service

SummaryTargetActual
Unplanned interruptions (score out of 10)Unplanned interruptions are issues such as gas escapes, which result in the gas going of suddenly and without warning. Each year, Ofgem carries out surveys among a cross-section of customers affected by such an interruption, to gauge their level of satisfaction with our response. Our score of 9.55 is ahead of target, and in line with our outperformance throughout RIIO GD1. The professionalism and dedication of our emergency engineers had a lot to do with this great performance.9.09.46
Planned interruptions (score out of 10)Planned interruptions are periods when the gas goes off for essential repair or maintenance work. Customers are given advanced notice, usually through letters. Our score of 8.92 is ahead of target and in line with our outperformance throughout much of RIIO GD1. Lots of elements went into this strong performance, including the use of detailed mitigation plans for each job, to minimise inconvenience, and weighting our programme of work, so that fewer jobs are carried out in winter, when the impact of losing gas is more acute.8.58.9
Connections (score out of 10)This is a measure of how we performed when installing private gas connections for homes or businesses. Our score of 9.05 out of 10 is ahead of our target and in line with our outperformance throughout RIIO GD1. We’ve transformed our connections service in recent years, to make it far more customer focused, and this is reflected in the strong score.8.49.16
Complaints metricWe receive an overall complaints score each year, based on four different elements: the percentage of complaints unresolved after one working day; percentage of complaints unresolved after 31 working days; percentage of repeat complaints and the number of Energy Ombudsman decisions that have gone against us.11.62.7

Year: Year: 2017/18

Customer Service

SummaryTargetActual
Unplanned interruptions (score out of 10)Unplanned interruptions are issues such as gas escapes, which result in the gas going of suddenly and without warning. Each year, Ofgem carries out surveys among a cross-section of customers affected by such an interruption, to gauge their level of satisfaction with our response. Our score of 9.55 is ahead of target, and in line with our outperformance throughout RIIO GD1. The professionalism and dedication of our emergency engineers had a lot to do with this great performance.9.09.45
Planned interruptions (score out of 10)Planned interruptions are periods when the gas goes off for essential repair or maintenance work. Customers are given advanced notice, usually through letters. Our score of 8.92 is ahead of target and in line with our outperformance throughout much of RIIO GD1. Lots of elements went into this strong performance, including the use of detailed mitigation plans for each job, to minimise inconvenience, and weighting our programme of work, so that fewer jobs are carried out in winter, when the impact of losing gas is more acute.8.58.85
Connections (score out of 10)This is a measure of how we performed when installing private gas connections for homes or businesses. Our score of 9.05 out of 10 is ahead of our target and in line with our outperformance throughout RIIO GD1. We’ve transformed our connections service in recent years, to make it far more customer focused, and this is reflected in the strong score.8.49.14
Complaints metricWe receive an overall complaints score each year, based on four different elements: the percentage of complaints unresolved after one working day; percentage of complaints unresolved after 31 working days; percentage of repeat complaints and the number of Energy Ombudsman decisions that have gone against us.11.63.4

Year: Year: 2018/19

Customer Service

SummaryTargetActual
Unplanned interruptions (score out of 10)Unplanned interruptions are issues such as gas escapes, which result in the gas going of suddenly and without warning. Each year, Ofgem carries out surveys among a cross-section of customers affected by such an interruption, to gauge their level of satisfaction with our response. Our score of 9.55 is ahead of target, and in line with our outperformance throughout RIIO GD1. The professionalism and dedication of our emergency engineers had a lot to do with this great performance.9.09.49
Planned interruptions (score out of 10)Planned interruptions are periods when the gas goes off for essential repair or maintenance work. Customers are given advanced notice, usually through letters. Our score of 8.92 is ahead of target and in line with our outperformance throughout much of RIIO GD1. Lots of elements went into this strong performance, including the use of detailed mitigation plans for each job, to minimise inconvenience, and weighting our programme of work, so that fewer jobs are carried out in winter, when the impact of losing gas is more acute.8.58.83
Connections (score out of 10)This is a measure of how we performed when installing private gas connections for homes or businesses. Our score of 9.05 out of 10 is ahead of our target and in line with our outperformance throughout RIIO GD1. We’ve transformed our connections service in recent years, to make it far more customer focused, and this is reflected in the strong score.8.48.93
Complaints metricWe receive an overall complaints score each year, based on four different elements: the percentage of complaints unresolved after one working day; percentage of complaints unresolved after 31 working days; percentage of repeat complaints and the number of Energy Ombudsman decisions that have gone against us.11.62.9

Year: Year: 2019/2020

Customer Service

SummaryTargetActual
Unplanned interruptions (score out of 10)Unplanned interruptions are issues such as gas escapes, which result in the gas going of suddenly and without warning. Each year, Ofgem carries out surveys among a cross-section of customers affected by such an interruption, to gauge their level of satisfaction with our response. Our score of 9.55 is ahead of target, and in line with our outperformance throughout RIIO GD1. The professionalism and dedication of our emergency engineers had a lot to do with this great performance.9.09.48
Planned interruptions (score out of 10)Planned interruptions are periods when the gas goes off for essential repair or maintenance work. Customers are given advanced notice, usually through letters. Our score of 8.92 is ahead of target and in line with our outperformance throughout much of RIIO GD1. Lots of elements went into this strong performance, including the use of detailed mitigation plans for each job, to minimise inconvenience, and weighting our programme of work, so that fewer jobs are carried out in winter, when the impact of losing gas is more acute.8.58.92
Connections (score out of 10)This is a measure of how we performed when installing private gas connections for homes or businesses. Our score of 9.05 out of 10 is ahead of our target and in line with our outperformance throughout RIIO GD1. We’ve transformed our connections service in recent years, to make it far more customer focused, and this is reflected in the strong score.8.49.05
Complaints metricWe receive an overall complaints score each year, based on four different elements: the percentage of complaints unresolved after one working day; percentage of complaints unresolved after 31 working days; percentage of repeat complaints and the number of Energy Ombudsman decisions that have gone against us.11.62.44

Year: Year: 2020/21

Customer Service

SummaryTargetActual
Unplanned interruptions (score out of 10)Unplanned interruptions are issues such as gas escapes, which result in the gas going of suddenly and without warning. Each year, Ofgem carries out surveys among a cross-section of customers affected by such an interruption, to gauge their level of satisfaction with our response. Our score of 9.55 is ahead of target, and in line with our outperformance throughout RIIO GD1. The professionalism and dedication of our emergency engineers had a lot to do with this great performance.9.09.55
Planned interruptions (score out of 10)Planned interruptions are periods when the gas goes off for essential repair or maintenance work. Customers are given advanced notice, usually through letters. Our score of 8.92 is ahead of target and in line with our outperformance throughout much of RIIO GD1. Lots of elements went into this strong performance, including the use of detailed mitigation plans for each job, to minimise inconvenience, and weighting our programme of work, so that fewer jobs are carried out in winter, when the impact of losing gas is more acute.8.58.92
Connections (score out of 10)This is a measure of how we performed when installing private gas connections for homes or businesses. Our score of 9.05 out of 10 is ahead of our target and in line with our outperformance throughout RIIO GD1. We’ve transformed our connections service in recent years, to make it far more customer focused, and this is reflected in the strong score.8.49.05
Complaints metricWe receive an overall complaints score each year, based on four different elements: the percentage of complaints unresolved after one working day; percentage of complaints unresolved after 31 working days; percentage of repeat complaints and the number of Energy Ombudsman decisions that have gone against us.11.62.40

Making the right connection

A gas connection is just one element of a bigger project, such as a new development or property extension. Customers reply on us to deliver a speedy, reliable service from their very first enquiry.

  • Year: 2013/14
  • Year: 2014/15
  • Year: 2015/16
  • Year: 2016/17
  • Year: 2017/18
  • Year: 2018/19
  • Year: 2019/20
  • Year: 2020/21

Year: Year: 2013/14

Connections

SummaryTargetActual
Percentage of connection jobs substantially completed on date agreed with the customerHitting our completion targets is really important for customers, especially as any delays to our work can have knock-on consequences for the customer’s wider project (e.g. a building extension or new build). Our 95% target was challenging, and we performed extremely well to exceed it.95%98.6%
Percentage of commencement and completion dates for connections above 275 kwh provided within 20 daysWe know that our customers have busy lives and that a new connection is often just one part of a wider project, so it’s important that we give as much notice as possible about when the work is due to start and finish so that customers can plan around the wider project. We strive to do this 100% of the time and we were pleased to deliver in 2020/21.100% (for connections above 275kwh)98.5%
% of commencement and completion dates for connections below 275kwh provided within 20 daysWe know that our customers have busy lives and that a new connection is often just one part of a wider project, so it’s important that we give as much notice as possible about when the work is due to start and finish so that customers can plan around the wider project. We just came in behind our annual target for connections below 275 kwh.99.6% (for connections below 275kwh)99.8%
Percentage of standard quotations issued in six working daysAs private connections are commercial transactions, we quote for each and every job. A speedy turnaround for quotes is important, especially as the gas connection is usually just one element of a wider project, such as a building extension. Delays from us can affect the whole timetable. We were just behind our 99.6% target in 2020/21.99.6%99.7%
% of non-standard connection quotes below 275kwh issued in 11 working daysA 99.6% target is very testing for this measure. A ‘non-standard’ connection often means a complex job, requiring significant research before we can provide an accurate quote. Unfortunately, we just missed out on hitting our target in 2020/21.99.6%99.6%
% of non-standard connection quotes above 275kwh issued in 21 working daysA 99.6% target is very testing for this measure. A ‘non-standard’ connection often means a complex job, requiring significant groundwork before we can provide an accurate quote. We missed our target this year.99.6%98.7%
% of land enquiries where response sent within 5 working daysUnfortunately, we missed out on hitting our target in 2020/21.99.6%99.6%

Year: Year: 2014/15

Connections

SummaryTargetActual
Percentage of connection jobs substantially completed on date agreed with the customerHitting our completion targets is really important for customers, especially as any delays to our work can have knock-on consequences for the customer’s wider project (e.g. a building extension or new build). Our 95% target was challenging, and we performed extremely well to exceed it.95%98.6%
Percentage of commencement and completion dates for connections above 275 kwh provided within 20 daysWe know that our customers have busy lives and that a new connection is often just one part of a wider project, so it’s important that we give as much notice as possible about when the work is due to start and finish so that customers can plan around the wider project. We strive to do this 100% of the time and we were pleased to deliver in 2020/21.100% (for connections above 275kwh)98.5%
% of commencement and completion dates for connections below 275kwh provided within 20 daysWe know that our customers have busy lives and that a new connection is often just one part of a wider project, so it’s important that we give as much notice as possible about when the work is due to start and finish so that customers can plan around the wider project. We just came in behind our annual target for connections below 275 kwh.99.6% (for connections below 275kwh)99.8%
Percentage of standard quotations issued in six working daysAs private connections are commercial transactions, we quote for each and every job. A speedy turnaround for quotes is important, especially as the gas connection is usually just one element of a wider project, such as a building extension. Delays from us can affect the whole timetable. We were just behind our 99.6% target in 2020/21.99.6%99.7%
% of non-standard connection quotes below 275kwh issued in 11 working daysA 99.6% target is very testing for this measure. A ‘non-standard’ connection often means a complex job, requiring significant research before we can provide an accurate quote. Unfortunately, we just missed out on hitting our target in 2020/21.99.6%99.6%
% of non-standard connection quotes above 275kwh issued in 21 working daysA 99.6% target is very testing for this measure. A ‘non-standard’ connection often means a complex job, requiring significant groundwork before we can provide an accurate quote. We missed our target this year.99.6%98.7%
% of land enquiries where response sent within 5 working daysUnfortunately, we missed out on hitting our target in 2020/21.99.6%99.6%

Year: Year: 2015/16

Connections

SummaryTargetActual
Percentage of connection jobs substantially completed on date agreed with the customerHitting our completion targets is really important for customers, especially as any delays to our work can have knock-on consequences for the customer’s wider project (e.g. a building extension or new build). Our 95% target was challenging, and we performed extremely well to exceed it.95%98.4%
Percentage of commencement and completion dates for connections above 275 kwh provided within 20 daysWe know that our customers have busy lives and that a new connection is often just one part of a wider project, so it’s important that we give as much notice as possible about when the work is due to start and finish so that customers can plan around the wider project. We strive to do this 100% of the time and we were pleased to deliver in 2020/21.100% (for connections above 275kwh)97.6%
% of commencement and completion dates for connections below 275kwh provided within 20 daysWe know that our customers have busy lives and that a new connection is often just one part of a wider project, so it’s important that we give as much notice as possible about when the work is due to start and finish so that customers can plan around the wider project. We just came in behind our annual target for connections below 275 kwh.99.6% (for connections below 275kwh)100%
Percentage of standard quotations issued in six working daysAs private connections are commercial transactions, we quote for each and every job. A speedy turnaround for quotes is important, especially as the gas connection is usually just one element of a wider project, such as a building extension. Delays from us can affect the whole timetable. We were just behind our 99.6% target in 2020/21.99.6%99.8%
% of non-standard connection quotes below 275kwh issued in 11 working daysA 99.6% target is very testing for this measure. A ‘non-standard’ connection often means a complex job, requiring significant research before we can provide an accurate quote. Unfortunately, we just missed out on hitting our target in 2020/21.99.6%99.8%
% of non-standard connection quotes above 275kwh issued in 21 working daysA 99.6% target is very testing for this measure. A ‘non-standard’ connection often means a complex job, requiring significant groundwork before we can provide an accurate quote. We missed our target this year.99.6%100%
% of land enquiries where response sent within 5 working daysUnfortunately, we missed out on hitting our target in 2020/21.99.6%100%

Year: Year: 2016/17

Connections

SummaryTargetActual
Percentage of connection jobs substantially completed on date agreed with the customerHitting our completion targets is really important for customers, especially as any delays to our work can have knock-on consequences for the customer’s wider project (e.g. a building extension or new build). Our 95% target was challenging, and we performed extremely well to exceed it.95%98.5%
Percentage of commencement and completion dates for connections above 275 kwh provided within 20 daysWe know that our customers have busy lives and that a new connection is often just one part of a wider project, so it’s important that we give as much notice as possible about when the work is due to start and finish so that customers can plan around the wider project. We strive to do this 100% of the time and we were pleased to deliver in 2020/21.100% (for connections above 275kwh)100%
% of commencement and completion dates for connections below 275kwh provided within 20 daysWe know that our customers have busy lives and that a new connection is often just one part of a wider project, so it’s important that we give as much notice as possible about when the work is due to start and finish so that customers can plan around the wider project. We just came in behind our annual target for connections below 275 kwh.99.6% (for connections below 275kwh)99.97%
Percentage of standard quotations issued in six working daysAs private connections are commercial transactions, we quote for each and every job. A speedy turnaround for quotes is important, especially as the gas connection is usually just one element of a wider project, such as a building extension. Delays from us can affect the whole timetable. We were just behind our 99.6% target in 2020/21.99.6%99.92%
% of non-standard connection quotes below 275kwh issued in 11 working daysA 99.6% target is very testing for this measure. A ‘non-standard’ connection often means a complex job, requiring significant research before we can provide an accurate quote. Unfortunately, we just missed out on hitting our target in 2020/21.99.6%99.85%
% of non-standard connection quotes above 275kwh issued in 21 working daysA 99.6% target is very testing for this measure. A ‘non-standard’ connection often means a complex job, requiring significant groundwork before we can provide an accurate quote. We missed our target this year.99.6%100%
% of land enquiries where response sent within 5 working daysUnfortunately, we missed out on hitting our target in 2020/21.99.6%99.43%

Year: Year: 2017/18

Connections

SummaryTargetActual
Percentage of connection jobs substantially completed on date agreed with the customerHitting our completion targets is really important for customers, especially as any delays to our work can have knock-on consequences for the customer’s wider project (e.g. a building extension or new build). Our 95% target was challenging, and we performed extremely well to exceed it.95%97.69%
Percentage of commencement and completion dates for connections above 275 kwh provided within 20 daysWe know that our customers have busy lives and that a new connection is often just one part of a wider project, so it’s important that we give as much notice as possible about when the work is due to start and finish so that customers can plan around the wider project. We strive to do this 100% of the time and we were pleased to deliver in 2020/21.100% (for connections above 275kwh)100%
% of commencement and completion dates for connections below 275kwh provided within 20 daysWe know that our customers have busy lives and that a new connection is often just one part of a wider project, so it’s important that we give as much notice as possible about when the work is due to start and finish so that customers can plan around the wider project. We just came in behind our annual target for connections below 275 kwh.99.6% (for connections below 275kwh)99.94%
Percentage of standard quotations issued in six working daysAs private connections are commercial transactions, we quote for each and every job. A speedy turnaround for quotes is important, especially as the gas connection is usually just one element of a wider project, such as a building extension. Delays from us can affect the whole timetable. We were just behind our 99.6% target in 2020/21.99.6%99.66%
% of non-standard connection quotes below 275kwh issued in 11 working daysA 99.6% target is very testing for this measure. A ‘non-standard’ connection often means a complex job, requiring significant research before we can provide an accurate quote. Unfortunately, we just missed out on hitting our target in 2020/21.99.6%99.52%
% of non-standard connection quotes above 275kwh issued in 21 working daysA 99.6% target is very testing for this measure. A ‘non-standard’ connection often means a complex job, requiring significant groundwork before we can provide an accurate quote. We missed our target this year.99.6%99.68%
% of land enquiries where response sent within 5 working daysUnfortunately, we missed out on hitting our target in 2020/21.99.6%98.26%

Year: Year: 2018/19

Connections

SummaryTargetActual
Percentage of connection jobs substantially completed on date agreed with the customerHitting our completion targets is really important for customers, especially as any delays to our work can have knock-on consequences for the customer’s wider project (e.g. a building extension or new build). Our 95% target was challenging, and we performed extremely well to exceed it.95%97.2%
Percentage of commencement and completion dates for connections above 275 kwh provided within 20 daysWe know that our customers have busy lives and that a new connection is often just one part of a wider project, so it’s important that we give as much notice as possible about when the work is due to start and finish so that customers can plan around the wider project. We strive to do this 100% of the time and we were pleased to deliver in 2020/21.100% (for connections above 275kwh)97.01%
% of commencement and completion dates for connections below 275kwh provided within 20 daysWe know that our customers have busy lives and that a new connection is often just one part of a wider project, so it’s important that we give as much notice as possible about when the work is due to start and finish so that customers can plan around the wider project. We just came in behind our annual target for connections below 275 kwh.99.6% (for connections below 275kwh)99.72%
Percentage of standard quotations issued in six working daysAs private connections are commercial transactions, we quote for each and every job. A speedy turnaround for quotes is important, especially as the gas connection is usually just one element of a wider project, such as a building extension. Delays from us can affect the whole timetable. We were just behind our 99.6% target in 2020/21.99.6%99.6%
% of non-standard connection quotes below 275kwh issued in 11 working daysA 99.6% target is very testing for this measure. A ‘non-standard’ connection often means a complex job, requiring significant research before we can provide an accurate quote. Unfortunately, we just missed out on hitting our target in 2020/21.99.6%99.4%
% of non-standard connection quotes above 275kwh issued in 21 working daysA 99.6% target is very testing for this measure. A ‘non-standard’ connection often means a complex job, requiring significant groundwork before we can provide an accurate quote. We missed our target this year.99.6%97.03%
% of land enquiries where response sent within 5 working daysUnfortunately, we missed out on hitting our target in 2020/21.99.6%100%

Year: Year: 2019/20

Connections

SummaryTargetActual
Percentage of connection jobs substantially completed on date agreed with the customerHitting our completion targets is really important for customers, especially as any delays to our work can have knock-on consequences for the customer’s wider project (e.g. a building extension or new build). Our 95% target was challenging, and we performed extremely well to exceed it.95%91.17%
Percentage of commencement and completion dates for connections above 275 kwh provided within 20 daysWe know that our customers have busy lives and that a new connection is often just one part of a wider project, so it’s important that we give as much notice as possible about when the work is due to start and finish so that customers can plan around the wider project. We strive to do this 100% of the time and we were pleased to deliver in 2020/21.100% (for connections above 275kwh)91.38%
% of commencement and completion dates for connections below 275kwh provided within 20 daysWe know that our customers have busy lives and that a new connection is often just one part of a wider project, so it’s important that we give as much notice as possible about when the work is due to start and finish so that customers can plan around the wider project. We just came in behind our annual target for connections below 275 kwh.99.6% (for connections below 275kwh)97.67%
Percentage of standard quotations issued in six working daysAs private connections are commercial transactions, we quote for each and every job. A speedy turnaround for quotes is important, especially as the gas connection is usually just one element of a wider project, such as a building extension. Delays from us can affect the whole timetable. We were just behind our 99.6% target in 2020/21.99.6%97.90%
% of non-standard connection quotes below 275kwh issued in 11 working daysA 99.6% target is very testing for this measure. A ‘non-standard’ connection often means a complex job, requiring significant research before we can provide an accurate quote. Unfortunately, we just missed out on hitting our target in 2020/21.99.6%97.67%
% of non-standard connection quotes above 275kwh issued in 21 working daysA 99.6% target is very testing for this measure. A ‘non-standard’ connection often means a complex job, requiring significant groundwork before we can provide an accurate quote. We missed our target this year.99.6%96.54%
% of land enquiries where response sent within 5 working daysUnfortunately, we missed out on hitting our target in 2020/21.99.6%97.12%

Year: Year: 2020/21

Connections

SummaryTargetActual
Percentage of connection jobs substantially completed on date agreed with the customerHitting our completion targets is really important for customers, especially as any delays to our work can have knock-on consequences for the customer’s wider project (e.g. a building extension or new build). Our 95% target was challenging, and we performed extremely well to exceed it.95%97.10%
Percentage of commencement and completion dates for connections above 275 kwh provided within 20 daysWe know that our customers have busy lives and that a new connection is often just one part of a wider project, so it’s important that we give as much notice as possible about when the work is due to start and finish so that customers can plan around the wider project. We strive to do this 100% of the time and we were pleased to deliver in 2020/21.100% (for connections above 275kwh)100%
% of commencement and completion dates for connections below 275kwh provided within 20 daysWe know that our customers have busy lives and that a new connection is often just one part of a wider project, so it’s important that we give as much notice as possible about when the work is due to start and finish so that customers can plan around the wider project. We just came in behind our annual target for connections below 275 kwh.99.6% (for connections below 275kwh)98.66%
Percentage of standard quotations issued in six working daysAs private connections are commercial transactions, we quote for each and every job. A speedy turnaround for quotes is important, especially as the gas connection is usually just one element of a wider project, such as a building extension. Delays from us can affect the whole timetable. We were just behind our 99.6% target in 2020/21.99.6%98.88%
% of non-standard connection quotes below 275kwh issued in 11 working daysA 99.6% target is very testing for this measure. A ‘non-standard’ connection often means a complex job, requiring significant research before we can provide an accurate quote. Unfortunately, we just missed out on hitting our target in 2020/21.99.6%98.55%
% of non-standard connection quotes above 275kwh issued in 21 working daysA 99.6% target is very testing for this measure. A ‘non-standard’ connection often means a complex job, requiring significant groundwork before we can provide an accurate quote. We missed our target this year.99.6%98.78%
% of land enquiries where response sent within 5 working daysUnfortunately, we missed out on hitting our target in 2020/21.99.6%98.55%

Keeping costs down without compromising service

Under the terms of our RIIO contract with Ofgem, we receive financial rewards for good performance in key areas – or penalties for falling short. We achieved significant rewards throughout RIIO-GD1 and no penalties, reinvesting in our business to deliver sustainable value for our region.

  • £18 million

    For great customer service. We exceeded all our customer satisfaction targets and handled complaints speedily and efficiently and were awarded £18 million to reinvest in our business and deliver further benefits for our customers.

  • £3.91 million

    For beating our pipe leakage targets. Beating the leaks is important for a smooth, safe service, and also prevents the build-up of harmful greenhouse gases.

  • £11 million

    For meeting our customers’ demands for gas, all year round – ensuring a reliable supply with few interruptions.

  • £9.2 million

    For our work with stakeholders to deliver shared goals

Zero penalties

By meeting our exceeding all our key regulatory targets, we incurred no financial penalties in RIIO-GD1.