UPDATE: Phase 1 (Milford Road) of the project will start on Monday 13 November and is scheduled to take approximately two-weeks.

Details about the project

We’re replacing the existing metal gas pipes in and around Cheshire Road, Stockton with more durable, plastic pipes that will keep you cooking on gas and your home warm for years to come.

We expect the work to start on Monday 13 November and to take 20-weeks, meaning we should be finished by mid-April, 2018. To help keep any inconvenience to a minimum, we have planned our work to be carried out in four phases (detailed below).

We’ll need to dig in the street but we’ll try to keep any inconvenience to a minimum and give you access to your home. Rest assured, we’ll put everything back to normal once we’ve finished. You can find out more about this by reading our reinstatement process leaflet (PDF document).

If you’re planning any exterior building work to your home or changes to your garden or driveway in the next six-months, please complete the form below or call our Customer Care Team on 0800 040 7766, so we can do what we can to plan these works around yours.

You can find out more about why we carry out these works by downloading our FAQs (PDF document).

If you have a disability or illness which means you might struggle without your gas supply, even for a few hours, it’s a good idea to get added to your gas supplier’s Priority Service Register.

Project phases

As part of the project, each road has been put into a phase (listed below). Alternatively, please download our phases map (PDF document).

Phase 1 (two-weeks)
  • Millford Road
Phase 2 (eight-weeks)
  • Raleigh Road
  • Clive Crescent
  • Waterford Road
  • Wolfe Road
  • Somerset Road
  • Drake Road
Phase 3 (seven-weeks)
  • Collins Avenue
  • Carmel Gardens
  • Cherry Tree Gardens
  • South Road
  • Berkshire Road (split between phases 3 and 4)
Phase 4 (eight-weeks)
  • Berkshire Road (split between phases 3 and 4)
  • Cheshire Road
  • Cornwall Grove
  • Huntington Green
  • Lincoln Grove
  • Warwick Grove