The Gas distributor for the North of England

Poplar Avenue, Dinnington

Current or Planned Work :Current
Project :Poplar Avenue, Dinnington
Expected Start Date :25th January 2009
Anticipated Duration : Approx 12 Weeks
Roads Affected :

Beech Avenue
Elm Avenue
Elm Court - Awaiting reinstatement
Ash Avenue
Ash Grove - Awaiting reinstatement
Oak Avenue
Poplar Avenue
Pine Avenue
Sycamore Avenue - in progress

Description and Updates :Project to replace metallic gas pipe with polyethylene pipe.
Customer Liaison Officer:Jacqueline Gibson
Gas Emergency Your Views Matter Dial before you dig
Copyright ©2011 Northern Gas Networks Limited