The Gas distributor for the North of England

Millcroft, Carlisle

Current or Planned Work :Current
Project :Longlands Road
Expected Start Date :28th September 2009
Anticipated Duration : End of November 2009
Roads Affected :

Longlands Road - Complete
Millcroft - Ongoing - Complete

Description and Updates :Project to replace metallic gas pipe with polyethylene pipe.
Customer Liaison Officer:Jackie Gibson
Gas Emergency Your Views Matter Dial before you dig
Copyright ©2011 Northern Gas Networks Limited