| Current or Planned Work : | Current |
| Project : | Cranbourne Road |
| Expected Start Date : | |
| Anticipated Duration : | End of December 2009 |
| Roads Affected : | Clift Street - Complete |
| Description and Updates : | Project to replace metallic gas pipe with polyethylene pipe. |
| Customer Liaison Officer: | Jackie Gibson |
![]() |
![]() |
![]() |