The Gas distributor for the North of England

Linthorpe Road, Middlesbrough

Current or Planned Work :Current
Project :

Linthorpe Road, Middlesbrough

Expected Start Date :4th April 2011
Anticipated Duration :  8 Weeks
Roads Affected :

Linthorpe Road
Benson Street
St Barnabas Road

 Description and Updates :The work involves replacing around 120m of gas mains and our contractors, Balfour Beatty, plan to start work on or around the 4th April with the work expecting to last up to eight weeks.
For any residents wishing to discuss the works or find out more information, a drop in session has been organised on Wednesday, 30 March 2011 in the Reid Room, St Barnabas Church Hall between 15.00 and 19.00 hrs.
The work will consist of lane closures on St Barnabas Road and Benson Street with diversion routes in operation.
Customer Liaison Officer:Jackie Gibson / Denise O'Donnell / Jacqueline Whittaker