| Current or Planned Work : | Current |
| Project : | Chesmond Drive, Blaydon On Tyne |
| Expected Start Date : | 23rd March 2009 |
| Anticipated Duration : | End of June |
| Roads Affected : | Tynebank - completed Thornton Crescent - completed Chesmond Drive - ongoing Ryshley Crescent - ongoing Broomlea Court - not affected Abingdon Court - not affected Juniper Court - completed Lawrence Avenue - completed Bedahill - completed Lawrence Court - completed Jobling Avenue - completed Cromwell Avenue - completed Hillside River View - completed Heddon View - completed Westway - completed Denton View - completed Wylan View - connection only |
| Description and Updates : | Project to replace metallic gas pipe with polyethylene pipe.
|
| Customer Liaison Officer: | Jackie Gibson |