George Hudson Street, York

Current or Planned Work :Planned
Project :George Hudson Street, York
Expected Start Date :20th April 2009
Anticipated Duration : 9 weeks
Roads Affected :

Marygate - complete
Marygate Lane
Hetherton Street
St Leonards Place - complete
High Petergate - work commenced
Minster Gates
Low Petergate
Stonegate

Description and Updates : 
Customer Liaison Officer:Amanda White