The Gas distributer for the North of England

Aldenham Gardens, North Sheilds

Current or Planned Work :Current
Project :Aldenham Gardens, North Sheilds
Expected Start Date :12th May 2008
Anticipated Duration : 26 weeks
Roads Affected :

Aldenham Gardens - work complete
Ashleigh Grove - work commenced
Crossway
Kennersdene - work complete
Marshmont Avenue - work complete
Millview Drive
Monks Way
Monkstone Crescent - work complete
The Broadway
Abbey Drive
Manor Road
Manorway
Parkside - work commenced
Parkside Crescent - work complete
Percy Park
Princeway
Seafield View
The Drive - ongoing
King Edward Road

Description and Updates :Project to replace metallic gas pipe with polyethylene pipe.
Playsafes to be arranged.
Customer Liaison Officer:Denise O'Donnell
Gas Emergency Improving your environment Dial before you dig
Copyright ©2007 Northern Gas Networks Limited