The Gas distributer for the North of England

Hereford Road, Guisborough

Current or Planned Work :Current
Project :Hereford Road, Guisborough
Expected Start Date :14th April 2008
Anticipated Duration : 13 weeks
Roads Affected :

Hereford Road - underway
Leven Road - complete
Avon Drive - complete
Derwent Avenue - complete
Severn Drive - complete
Lewis Walk - reinstatement underway
Thames Avenue - ongoing
Dorset Road
Stafford Road

Description and Updates :

Project to replace metallic gas pipe with polyethylene pipe.
Playsafes taking place in the area.

Road sweeper will used once project complete

Customer Liaison Officer:Jackie Gibson
Gas Emergency Improving your environment Dial before you dig
Copyright ©2007 Northern Gas Networks Limited